We’d like to remind Forumites to please avoid political debate on the Forum.

This is to keep it a safe and useful space for MoneySaving discussions. Threads that are – or become – political in nature may be removed in line with the Forum’s rules. Thank you for your understanding.

IMPORTANT: Please make sure your posts do not contain any personally identifiable information (both your own and that of others). When uploading images, please take care that you have redacted all personal information including number plates, reference numbers and QR codes (which may reveal vehicle information when scanned).
📨 Have you signed up to the Forum's new Email Digest yet? Get a selection of trending threads sent straight to your inbox daily, weekly or monthly!
The Forum now has a brand new text editor, adding a bunch of handy features to use when creating posts. Read more in our how-to guide

CCJ PARKING FINE DEFENCE HELP NEEDED

12346

Comments

  • Even better girl power 🦸‍♀️! 

    I will give a non-gender specific thanks to everyone who has helped me and all of us on the forum.

  • Hi All 


    I’ve just received this email below from DCB Legal and I am wondering how to respond?







    We write to you in relation to the above matter.

     

    To assist the Court in achieving its overriding objective, our Client may be prepared to settle this case. I can confirm our Client would be agreeable to £160 in full and final settlement of this Claim. The current outstanding balance is £278.12 

       

    Should you be agreeable to this offer, please confirm the same within 7 daysPayment can be made via our website www.dcblegal.co.uk, by calling our office on 0203 434 0424 or via bank transfer: 

        DCB Legal Ltd Client Account    Sort Code: 20-24-09  Account no: 60964441  
  • Coupon-mad
    Coupon-mad Posts: 162,305 Forumite
    Part of the Furniture 10,000 Posts Name Dropper Photogenic
    You've seemingly missed the DCBLegal thread by @Umkomaas that tells you what happens next?
    PRIVATE 'PCN'? DON'T PAY BUT DON'T IGNORE IT (except N.Ireland).
    CLICK at the top or bottom of any page where it says:
    Home»Motoring»Parking Tickets Fines & Parking - read the NEWBIES THREAD
  • Thanks Coupon-mad

    Yes I have missed the thread what course of action should I take?

    You gave me a fantastic response last time or should I just ignore this time?
  • Coupon-mad
    Coupon-mad Posts: 162,305 Forumite
    Part of the Furniture 10,000 Posts Name Dropper Photogenic
    Read his thread, is what to do.
    PRIVATE 'PCN'? DON'T PAY BUT DON'T IGNORE IT (except N.Ireland).
    CLICK at the top or bottom of any page where it says:
    Home»Motoring»Parking Tickets Fines & Parking - read the NEWBIES THREAD
  • I’ve received a court date of February 2023 when do I need my WS to be in by?
  • KeithP
    KeithP Posts: 41,296 Forumite
    Part of the Furniture 10,000 Posts Name Dropper
    I’ve received a court date of February 2023 when do I need my WS to be in by?

    Look again at your Notice of Allocation. The Notice that gives the hearing date.
    Is there not a paragraph something like:
    Each party must deliver to every other party and to the court office copies of all documents on which he intends to rely at the hearing no later than [ . . . ] [14 days before the hearing].
    Might be on the back.
    Those documents you intend to rely on are your Witness Statement and evidence.
  • Perfect thanks Keith P.

    It states 14 days before hearing.
  • Hi All

    It appears that they have discontinued?

    Should I double check with the court?




  • Mouse007
    Mouse007 Posts: 1,062 Forumite
    Part of the Furniture 1,000 Posts Photogenic Name Dropper
    You've seemingly missed the DCBLegal thread by @Umkomaas that tells you what happens next?

    Prediction came true, again

    Well done, over to @Umkomaas

    BBC WatchDog “if you are struggling with an unfair parking charge do get in touch”


    Please email your PCN story to watchdog@bbc.co.uk they want to hear about it.
    Please then tell us here that you have done so.

Meet your Ambassadors

🚀 Getting Started

Hi new member!

Our Getting Started Guide will help you get the most out of the Forum

Categories

  • All Categories
  • 354.6K Banking & Borrowing
  • 254.5K Reduce Debt & Boost Income
  • 455.5K Spending & Discounts
  • 247.5K Work, Benefits & Business
  • 604.4K Mortgages, Homes & Bills
  • 178.6K Life & Family
  • 261.9K Travel & Transport
  • 1.5M Hobbies & Leisure
  • 16.1K Discuss & Feedback
  • 37.7K Read-Only Boards

Is this how you want to be seen?

We see you are using a default avatar. It takes only a few seconds to pick a picture.