Quote to re-do my bathroom. What do you think?

Hi,

I received the quote below from a builder i know. I know it is not excessive, but he's supposed to give me a good price as he works for the company i work for.
I had my bathroom entirely re-done 3 yeard ago and i am sure i paid less for works...
What do you think?


-STRIP ALL OLD BATHROOM SUIT,PAPER ,TILES ,BOXING IN -£350
- REPLASTER ALL BATHROOM INCLUDES MATERIALS-£400
-SUPPLY AND FIT NEW PIPEWORK FOR BATHROOM TO FIT NEW LAY OUT-£350
-INSTALL NEW BATHROOM SUIT-£500
-INSTALL NEW TOWEL RAIL( INCLUDES DRAIN SISTEM AND RETOP UP) WITCH YOU SUPPLY INCLUDES PIPES AND FITINGS- £ 150

-TAILING BATHROOM AT £ 40/SQM INCLUDES ADHESIVE,GROUT AND SPACERS
-PAINT BATHROOM WITH PAINT YOU SUPPLY-£180
- NEW BOXING IN FOR PIPES AT LOW LEVEL INCLUDES MATERIALS-£ 250
-CLEAN AND DISPOSE ALL RUBISH RESULTING FROM DEMOLUTION-£ 150
«13

Comments

  • zweety wrote: »
    Hi,

    I received the quote below from a builder i know. I know it is not excessive, but he's supposed to give me a good price as he works for the company i work for.
    I had my bathroom entirely re-done 3 yeard ago and i am sure i paid less for works...
    What do you think?


    -STRIP ALL OLD BATHROOM SUIT,PAPER ,TILES ,BOXING IN -£350
    - REPLASTER ALL BATHROOM INCLUDES MATERIALS-£400
    -SUPPLY AND FIT NEW PIPEWORK FOR BATHROOM TO FIT NEW LAY OUT-£350
    -INSTALL NEW BATHROOM SUIT-£500
    -INSTALL NEW TOWEL RAIL( INCLUDES DRAIN SISTEM AND RETOP UP) WITCH YOU SUPPLY INCLUDES PIPES AND FITINGS- £ 150

    -TAILING BATHROOM AT £ 40/SQM INCLUDES ADHESIVE,GROUT AND SPACERS
    -PAINT BATHROOM WITH PAINT YOU SUPPLY-£180
    - NEW BOXING IN FOR PIPES AT LOW LEVEL INCLUDES MATERIALS-£ 250
    -CLEAN AND DISPOSE ALL RUBISH RESULTING FROM DEMOLUTION-£ 150


    So this includes all materials except a towel rail ?
    how long does he say the job will take ?
    Around here general builder charge between £120 and £150 a day and most would consider this a 5 day job dependant on the size .
    get 3 quotes and ask for details of previous jobs ..
  • zweety
    zweety Posts: 61 Forumite
    Part of the Furniture Combo Breaker
    They said it would take 2 weeks. Which is odd as the bathroom is tiny. I'm sure it took only a week when i had it done 3 years ago...
  • zweety
    zweety Posts: 61 Forumite
    Part of the Furniture Combo Breaker
    1 -So this includes all materials except a towel rail ?
    IT INCLUDES ALL MATERIALS EXCEPT TOWEL RAIL, BATHROOM SUITE, BATH PANEL, TILES AND PAINT

    2- how long does he say the job will take ?
    TOW WEEKS (It's a tiny bathroom)
  • giraffe69
    giraffe69 Posts: 3,613 Forumite
    Part of the Furniture 1,000 Posts Photogenic Name Dropper
    A similar job took 5 days for us and included fitting a new shower as well. The price wasn't that different.
  • zweety wrote: »
    Hi,

    I received the quote below from a builder i know. I know it is not excessive, but he's supposed to give me a good price as he works for the company i work for.
    I had my bathroom entirely re-done 3 yeard ago and i am sure i paid less for works...
    What do you think?


    -STRIP ALL OLD BATHROOM SUIT,PAPER ,TILES ,BOXING IN -£350
    - REPLASTER ALL BATHROOM INCLUDES MATERIALS-£400
    -SUPPLY AND FIT NEW PIPEWORK FOR BATHROOM TO FIT NEW LAY OUT-£350
    -INSTALL NEW BATHROOM SUIT-£500
    -INSTALL NEW TOWEL RAIL( INCLUDES DRAIN SISTEM AND RETOP UP) WITCH YOU SUPPLY INCLUDES PIPES AND FITINGS- £ 150

    -TAILING BATHROOM AT £ 40/SQM INCLUDES ADHESIVE,GROUT AND SPACERS
    -PAINT BATHROOM WITH PAINT YOU SUPPLY-£180
    - NEW BOXING IN FOR PIPES AT LOW LEVEL INCLUDES MATERIALS-£ 250
    -CLEAN AND DISPOSE ALL RUBISH RESULTING FROM DEMOLUTION-£ 150



    He is taking the p***
    Not Again
  • 1984ReturnsForReal_2
    1984ReturnsForReal_2 Posts: 15,431 Forumite
    edited 10 November 2010 at 12:14PM
    zweety wrote: »
    Hi,

    I received the quote below from a builder i know. I know it is not excessive, but he's supposed to give me a good price as he works for the company i work for.
    I had my bathroom entirely re-done 3 yeard ago and i am sure i paid less for works...
    What do you think?


    -STRIP ALL OLD BATHROOM SUIT,PAPER ,TILES ,BOXING IN [STRIKE]-£350[/STRIKE] £300
    - REPLASTER ALL BATHROOM INCLUDES MATERIALS[STRIKE]-£400[/STRIKE] £250????????
    -SUPPLY AND FIT NEW PIPEWORK FOR BATHROOM TO FIT NEW LAY OUT-[STRIKE]£350[/STRIKE] £200
    -INSTALL NEW BATHROOM SUIT-[STRIKE]£500[/STRIKE] £300
    -INSTALL NEW TOWEL RAIL( INCLUDES DRAIN SISTEM AND RETOP UP) WITCH YOU SUPPLY INCLUDES PIPES AND FITINGS- [STRIKE]£ 150 [/STRIKE] £80

    -TAILING BATHROOM AT [STRIKE]£ 40/SQM[/STRIKE]£30 INCLUDES ADHESIVE,GROUT AND SPACERS
    -PAINT BATHROOM WITH PAINT YOU SUPPLY-£180
    - NEW BOXING IN FOR PIPES AT LOW LEVEL INCLUDES MATERIALS[STRIKE]-£ 250[/STRIKE] £100
    [STRIKE] -CLEAN AND DISPOSE ALL RUBISH RESULTING FROM DEMOLUTION-£ 150[/STRIKE] Included in initial cost of strip out


    You said small bathroom & I take that to mean normal size.
    Not Again
  • suisidevw
    suisidevw Posts: 2,256 Forumite
    I had a very similiar job done and it took 10 days. It WON'T be done in 5!
  • zweety
    zweety Posts: 61 Forumite
    Part of the Furniture Combo Breaker
    The bathroom is roughly: 167cm x 190cm. and the boxing for pipes are about 20cm wide over an entire wall and corner...
  • Niv
    Niv Posts: 2,566 Forumite
    Part of the Furniture 1,000 Posts Name Dropper
    I consider this expensive/rip off. You said this was a 'deal' price due to you working for the company? Please post the company name so i can avoid them :-)

    Lets take one item £180 for painting the room with paint you supply AFTER seperatly paying for him to prepare the wall. So small bathroom with tiling, doorway and I assume a window and its 180quid? what is the wall area to be painted?
    YNWA

    Target: Mortgage free by 58.
  • Niv wrote: »
    I consider this expensive/rip off. You said this was a 'deal' price due to you working for the company? Please post the company name so i can avoid them :-)

    Lets take one item £180 for painting the room with paint you supply AFTER seperatly paying for him to prepare the wall. So small bathroom with tiling, doorway and I assume a window and its 180quid? what is the wall area to be painted?



    2 visits for a painter.

    £180 is the only thing that isnt a rip off.
    Not Again
This discussion has been closed.
Meet your Ambassadors

🚀 Getting Started

Hi new member!

Our Getting Started Guide will help you get the most out of the Forum

Categories

  • All Categories
  • 352.1K Banking & Borrowing
  • 253.5K Reduce Debt & Boost Income
  • 454.2K Spending & Discounts
  • 245.1K Work, Benefits & Business
  • 600.7K Mortgages, Homes & Bills
  • 177.4K Life & Family
  • 258.9K Travel & Transport
  • 1.5M Hobbies & Leisure
  • 16.2K Discuss & Feedback
  • 37.6K Read-Only Boards

Is this how you want to be seen?

We see you are using a default avatar. It takes only a few seconds to pick a picture.