We'd like to remind Forumites to please avoid political debate on the Forum... Read More »
3-phase electricity in a private road
I submitted an application and payment to our DNO, Scottish and Southern Electricity Networks (SSEN) in early April 2025, and an installation date was agreed. However, I was later informed that due to unresolved wayleave issues
WSP, acting on behalf of SSEN, has advised that a wayleave is required because the cable route crosses privately owned verge or access land. The road is private and it is now maintained by the road association (the chair of the road association has given us permission to dig under the road to connect to the supply). All the homeowners on the road pay an annual sub to maintain the road. However, WSP cannot accept that the road association is the freeholder of the road - the freeholder died decades ago. We cannot find the executor of the deceased freeholder in order to transfer ownership of the road to the road association.
To my knowledge, at least one neighbouring property on the road have installed a three-phase connection from SSEN without a formal wayleave being in place. But the rep from WSP has stated that the way in which a job has been completed historically does not infer precedent for any future works which are proposed to be completed. So, they are insisting on the freeholder to give approval.
Has anybody come across this issue?
Comments
-
Looks like you either trace the freeholder or go to court.
WSP are correct in that just because something has been done in the past, doesn't mean that it can be done now.
Let's Be Careful Out There0 -
HillStreetBlues said:Looks like you either trace the freeholder or go to court.
WSP are correct in that just because something has been done in the past, doesn't mean that it can be done now.0 -
HillStreetBlues said:Looks like you either trace the freeholder or go to court.N. Hampshire, he/him. Octopus Intelligent Go elec & Tracker gas / Vodafone BB / iD mobile. Ripple Kirk Hill member.
2.72kWp PV facing SSW installed Jan 2012. 11 x 247w panels, 3.6kw inverter. 34 MWh generated, long-term average 2.6 Os.Not exactly back from my break, but dipping in and out of the forum.Ofgem cap table, Ofgem cap explainer. Economy 7 cap explainer. Gas vs E7 vs peak elec heating costs, Best kettle!0 -
QrizB said:HillStreetBlues said:Looks like you either trace the freeholder or go to court.
Let's Be Careful Out There0 -
phuthu said:
I submitted an application and payment to our DNO, Scottish and Southern Electricity Networks (SSEN) in early April 2025, and an installation date was agreed. However, I was later informed that due to unresolved wayleave issues
WSP, acting on behalf of SSEN, has advised that a wayleave is required because the cable route crosses privately owned verge or access land. The road is private and it is now maintained by the road association (the chair of the road association has given us permission to dig under the road to connect to the supply). All the homeowners on the road pay an annual sub to maintain the road. However, WSP cannot accept that the road association is the freeholder of the road - the freeholder died decades ago. We cannot find the executor of the deceased freeholder in order to transfer ownership of the road to the road association.
To my knowledge, at least one neighbouring property on the road have installed a three-phase connection from SSEN without a formal wayleave being in place. But the rep from WSP has stated that the way in which a job has been completed historically does not infer precedent for any future works which are proposed to be completed. So, they are insisting on the freeholder to give approval.
Has anybody come across this issue?
If it is in the road the likely dimensions will be 2M × 1M and depth to range from 75mm to 1.2M
Have they set any conditions for on going maintenance if you manage to have it excavated0 -
The cable is under the grass verge on the other side of the road.0
-
35har1old said:phuthu said:
I submitted an application and payment to our DNO, Scottish and Southern Electricity Networks (SSEN) in early April 2025, and an installation date was agreed. However, I was later informed that due to unresolved wayleave issues
WSP, acting on behalf of SSEN, has advised that a wayleave is required because the cable route crosses privately owned verge or access land. The road is private and it is now maintained by the road association (the chair of the road association has given us permission to dig under the road to connect to the supply). All the homeowners on the road pay an annual sub to maintain the road. However, WSP cannot accept that the road association is the freeholder of the road - the freeholder died decades ago. We cannot find the executor of the deceased freeholder in order to transfer ownership of the road to the road association.
To my knowledge, at least one neighbouring property on the road have installed a three-phase connection from SSEN without a formal wayleave being in place. But the rep from WSP has stated that the way in which a job has been completed historically does not infer precedent for any future works which are proposed to be completed. So, they are insisting on the freeholder to give approval.
Has anybody come across this issue?
If it is in the road the likely dimensions will be 2M × 1M and depth to range from 75mm to 1.2M
Have they set any conditions for on going maintenance if you manage to have it excavated0 -
phuthu said:35har1old said:phuthu said:
I submitted an application and payment to our DNO, Scottish and Southern Electricity Networks (SSEN) in early April 2025, and an installation date was agreed. However, I was later informed that due to unresolved wayleave issues
WSP, acting on behalf of SSEN, has advised that a wayleave is required because the cable route crosses privately owned verge or access land. The road is private and it is now maintained by the road association (the chair of the road association has given us permission to dig under the road to connect to the supply). All the homeowners on the road pay an annual sub to maintain the road. However, WSP cannot accept that the road association is the freeholder of the road - the freeholder died decades ago. We cannot find the executor of the deceased freeholder in order to transfer ownership of the road to the road association.
To my knowledge, at least one neighbouring property on the road have installed a three-phase connection from SSEN without a formal wayleave being in place. But the rep from WSP has stated that the way in which a job has been completed historically does not infer precedent for any future works which are proposed to be completed. So, they are insisting on the freeholder to give approval.
Has anybody come across this issue?
If it is in the road the likely dimensions will be 2M × 1M and depth to range from 75mm to 1.2M
Have they set any conditions for on going maintenance if you manage to have it excavated0
Confirm your email address to Create Threads and Reply

Categories
- All Categories
- 350.9K Banking & Borrowing
- 253.1K Reduce Debt & Boost Income
- 453.5K Spending & Discounts
- 243.9K Work, Benefits & Business
- 598.8K Mortgages, Homes & Bills
- 176.9K Life & Family
- 257.2K Travel & Transport
- 1.5M Hobbies & Leisure
- 16.1K Discuss & Feedback
- 37.6K Read-Only Boards