We'd like to remind Forumites to please avoid political debate on the Forum... Read More »
Extra solar install, how does export work ?

nologo
Posts: 178 Forumite

I have a 4.6 kW solar roof system installed 3 years ago with a 5kW export permit from the Dno.
Next week a 5.9 kW solar system is going on my roof with separate inverter, by a mcs installer with a new 5kW dno Permit. It will have a seperate generation meter,
I export to Octopus @15p so when my solar is installed ,do I need to inform Octopus ,show mcs paperwork,? I have a smart meter and 2nd mpan, TIA
regards nologo
Next week a 5.9 kW solar system is going on my roof with separate inverter, by a mcs installer with a new 5kW dno Permit. It will have a seperate generation meter,
I export to Octopus @15p so when my solar is installed ,do I need to inform Octopus ,show mcs paperwork,? I have a smart meter and 2nd mpan, TIA
regards nologo
Deepest Kent. 4.6kW Growatt inverter, solar i boost+ 5.9kW Solar Edge
ok so far...
ok so far...
0
Comments
-
No. Your existing smart meter will measure your cumulative export so Octopus will pay you as normal.1
-
I disagree. You were accepted onto the Octopus tariff for your existing solar system and would have had to provide them with details of the MCS accreditation. If you are adding more panels you ought to tell Octopus.
Also, "a new 5kW dno permit" surely just allows you to export 5 kW? You need a 10 kW DNO permit to cover your total export.Reed1 -
Hi nologo. Have to say I find that a bit confusing. If it's a second mpan, then isn't it a separate account and a second smart meter too? Hence the 'new' 5kW export, rather than revised up to 10kW?Mart. Cardiff. 8.72 kWp PV systems (2.12 SSW 4.6 ESE & 2.0 WNW). 20kWh battery storage. Two A2A units for cleaner heating. Two BEV's for cleaner driving.
For general PV advice please see the PV FAQ thread on the Green & Ethical Board.0 -
What your DNO is concerned about is the capacity of the wires that supply your dwelling. If all the exported electricity goes through the same wires then you need DNO permission for the total.Reed0
-
thanks for all your advice, just to clarify,
I already had a 5kW export permit,
The new solar install will have an additional permit,
l already have the export mpan from my previous installation, not an additional account..
regards nologoDeepest Kent. 4.6kW Growatt inverter, solar i boost+ 5.9kW Solar Edge
ok so far...0 -
Reed_Richards said:What your DNO is concerned about is the capacity of the wires that supply your dwelling. If all the exported electricity goes through the same wires then you need DNO permission for the total.
This may sound like the same thing, but it's akin to neighbouring properties (that share a line upstream) each having a separate export limit. The DNO will need to consider the sum of SSEG's, and export limits approved, but each individual mpan approval/limit would be separate.
[Just a small technicality, but the DNO isn't really concerned about the capacity of the wires, since these are able to cope with far higher import amounts. They are concerned about the local area being able to absorb the theoretical max export from the SSEG / sum of SSEG's.]Mart. Cardiff. 8.72 kWp PV systems (2.12 SSW 4.6 ESE & 2.0 WNW). 20kWh battery storage. Two A2A units for cleaner heating. Two BEV's for cleaner driving.
For general PV advice please see the PV FAQ thread on the Green & Ethical Board.0 -
I still don't think you can have an "additional permit". If you want to export 10 kW you need a 10 kW permit. Having two 5 kW permits just lets you export 5 kW.Reed1
-
nologo said:thanks for all your advice, just to clarify,
I already had a 5kW export permit,
The new solar install will have an additional permit,
l already have the export mpan from my previous installation, not an additional account..
regards nologo
Edit - Ahhhhhhhh do you mean a second mpan by counting the import and export accounts separately? If so, then that's still one connection. I also have an export mpan number, as I assume do all people with registered SSEG's, but my two fully separate PV systems still needed a DNO approval equal to their sum.
Perhaps something is just getting lost in translation here?Mart. Cardiff. 8.72 kWp PV systems (2.12 SSW 4.6 ESE & 2.0 WNW). 20kWh battery storage. Two A2A units for cleaner heating. Two BEV's for cleaner driving.
For general PV advice please see the PV FAQ thread on the Green & Ethical Board.0 -
Even assuming that we can clear up the "translation" issues, I still think Octopus needs to know. If you have told them that you have a system that can export a maximum 5 kW then that's 5 kWh per hour or 2.5 kWh per half-hourly reading. So if Octopus start getting half-hourly export readings that frequently exceed 2.5 kWh what do they do?
- Continue export payments as normal?
- Limit the export payment for those "anomalous" half hours to the payment for 2.5 kWh?
- Stop the payments because the system isn't behaving as declared?
Reed0 -
thanks again for all your suggestions, I have now emailed
octopus. to find out..Deepest Kent. 4.6kW Growatt inverter, solar i boost+ 5.9kW Solar Edge
ok so far...0
Confirm your email address to Create Threads and Reply

Categories
- All Categories
- 350K Banking & Borrowing
- 252.7K Reduce Debt & Boost Income
- 453.1K Spending & Discounts
- 243K Work, Benefits & Business
- 619.9K Mortgages, Homes & Bills
- 176.4K Life & Family
- 255.9K Travel & Transport
- 1.5M Hobbies & Leisure
- 16.1K Discuss & Feedback
- 15.1K Coronavirus Support Boards