We'd like to remind Forumites to please avoid political debate on the Forum... Read More »
We're aware that some users are experiencing technical issues which the team are working to resolve. Thank you for your patience.
📨 Have you signed up to the Forum's new Email Digest yet? Get a selection of trending threads sent straight to your inbox daily, weekly or monthly!
How to force utility company to install a working smart meter
Options
Comments
-
Thanks everyone for taking time in answering. The meters has perfect coverage; I can even see the signal on the screen. However, the issue is that it was never registered properly. I have a small EV that I purchased to cut down on fuel costs, but I was never able to access the EV tariffs despite having a smart meter. Additionally, I cannot access the tracker or agile tariffs because the meter doesn't send the readings—not due to any fault, but because it was never registered. This is what the EDF engineer told me. It is a generation 1.0
-
There were a limited number of smets1 meters that were not able to be enrolled into the DCC network.Have you checked yours ?See the CAB link integration checker - from their websiteThere is meant to be a plan in place to upgrade those that cannot be modified - to smets2 - but as DCC states - it's not only up to them - but your supplier.But the integration and replacement program for that - I thought both - started a couple of years ago.From the DCC 2023 annual report"At the end of this financial year we had migrated 11.3m SMETS1, up from 8.9m in March 2022"I suspect for now - you will have to wait for Octopus to find a slot - swapping and restarting the queue at another supplier - is likely only to prolong the delay.
0 -
DE_612183 said:badmemory said:This is the problem with smart meters. Well the requirements for fitting them really. Their only requirement appears to be to fit them & not that they should actually work properly.0
-
Qyburn said:DE_612183 said:badmemory said:This is the problem with smart meters. Well the requirements for fitting them really. Their only requirement appears to be to fit them & not that they should actually work properly.0
-
Scot_39 said:There were a limited number of smets1 meters that were not able to be enrolled into the DCC network.Have you checked yours ?See the CAB link integration checker - from their websiteThere is meant to be a plan in place to upgrade those that cannot be modified - to smets2 - but as DCC states - it's not only up to them - but your supplier.But the integration and replacement program for that - I thought both - started a couple of years ago.From the DCC 2023 annual report"At the end of this financial year we had migrated 11.3m SMETS1, up from 8.9m in March 2022"I suspect for now - you will have to wait for Octopus to find a slot - swapping and restarting the queue at another supplier - is likely only to prolong the delay.
We can’t find your meter
This could be because:
- there was something wrong with your details - try entering them again.
- your meter isn’t on the smart meter data network, which connects your smart meter to energy suppliers
- you don’t have a smart meter - ask your supplier if you’re not sure
Now I have left octopus after waiting 4 months for a meter upgrade.0 -
DE_612183 said:Is it the smart meter that won't work or the in house display?0
-
Scot_39 said:There is meant to be a plan in place to upgrade those that cannot be modified - to smets2 - but as DCC states - it's not only up to them - but your supplier.One thing the OP should bear in mind is that all Smart meters have a certification life of 10 years, unless the manufacturer has done a component reliability study and obtained approval for a longer certification period. The SMETS1 standard was defined in 2012 with the first meters put on the wall a year or two later - so the first SMETS1’s will soon be coming to the end of their certification - I suspect these are the ones which will be replaced first.So depending on when the OPs SMETS1 meter was installed, they might be due for a replacement soon anyway.List of meters and their certification period available here:0
-
Kid_Icarus said:Scot_39 said:There is meant to be a plan in place to upgrade those that cannot be modified - to smets2 - but as DCC states - it's not only up to them - but your supplier.One thing the OP should bear in mind is that all Smart meters have a certification life of 10 years, unless the manufacturer has done a component reliability study and obtained approval for a longer certification period. The SMETS1 standard was defined in 2012 with the first meters put on the wall a year or two later - so the first SMETS1’s will soon be coming to the end of their certification - I suspect these are the ones which will be replaced first.So depending on when the OPs SMETS1 meter was installed, they might be due for a replacement soon anyway.List of meters and their certification period available here:
0 -
Paul_Sparrow said:Kid_Icarus said:Scot_39 said:There is meant to be a plan in place to upgrade those that cannot be modified - to smets2 - but as DCC states - it's not only up to them - but your supplier.One thing the OP should bear in mind is that all Smart meters have a certification life of 10 years, unless the manufacturer has done a component reliability study and obtained approval for a longer certification period. The SMETS1 standard was defined in 2012 with the first meters put on the wall a year or two later - so the first SMETS1’s will soon be coming to the end of their certification - I suspect these are the ones which will be replaced first.So depending on when the OPs SMETS1 meter was installed, they might be due for a replacement soon anyway.List of meters and their certification period available here:
I'm wondering if you could approach a different supplier and tell them you're planning to move to Economy 7 and need a new meter and see if that works? You'll need to tell them you're going to install night storage heaters. Once you have a new meter you can easily enough switch tariffs - although Economy 7 might be a good option anyway. Obviously not very honest but although I'm usually a rule-follower in your circumstances I'd be quite comfortable trying to find a way round the rules.
0 -
mmmmikey said:Paul_Sparrow said:Kid_Icarus said:Scot_39 said:There is meant to be a plan in place to upgrade those that cannot be modified - to smets2 - but as DCC states - it's not only up to them - but your supplier.One thing the OP should bear in mind is that all Smart meters have a certification life of 10 years, unless the manufacturer has done a component reliability study and obtained approval for a longer certification period. The SMETS1 standard was defined in 2012 with the first meters put on the wall a year or two later - so the first SMETS1’s will soon be coming to the end of their certification - I suspect these are the ones which will be replaced first.So depending on when the OPs SMETS1 meter was installed, they might be due for a replacement soon anyway.List of meters and their certification period available here:
I'm wondering if you could approach a different supplier and tell them you're planning to move to Economy 7 and need a new meter and see if that works? You'll need to tell them you're going to install night storage heaters. Once you have a new meter you can easily enough switch tariffs - although Economy 7 might be a good option anyway. Obviously not very honest but although I'm usually a rule-follower in your circumstances I'd be quite comfortable trying to find a way round the rules.EDF are the best currently, Octopus doesn't have engineers available at the moment in west wales and I was waiting months. Eon directly told me that they would send out no one despite their sales person telling me the opposite and pretending she could see available appointments in my area...
0
Confirm your email address to Create Threads and Reply

Categories
- All Categories
- 350.7K Banking & Borrowing
- 253K Reduce Debt & Boost Income
- 453.4K Spending & Discounts
- 243.6K Work, Benefits & Business
- 598.4K Mortgages, Homes & Bills
- 176.8K Life & Family
- 256.8K Travel & Transport
- 1.5M Hobbies & Leisure
- 16.1K Discuss & Feedback
- 37.6K Read-Only Boards