Laying carpet on quarry tiles

2 Posts
I'm after some advice from you knowledgeable folks.
I'm doing a refurb of an early 1900s terraced house, which has quarry tiles laid on ash in the dining room and kitchen. On reflection, I should have dug the tiles up and laid a concrete slab with a damp proof membrane. This didn't happen unfortunately. I was guided by someone that turned out to be a cowboy builder in the true sense of the phrase, and he assured me that a liquid damp proof treatment over the tiles has been adequate to prevent any dampness coming through on previous homes he has worked on. I didn't know at that time if dampness was indeed rising through the floor as I had only purchased the house a couple of months previous. The tiles were wet when I lifted the laminate floor and fibreboard that was underneath, but that may have been due to sweating. The floor quickly dried out in the days that followed, and there were no signs of dampness over the summer months while the tiles were exposed and the rest of the refurb was progressing.
The builder did pour on a liquid damp proof membrane, followed by a self-levelling screed, the latter being extremely badly applied (it was essentially tipped onto the floor and allowed run to the lowest point, where it congealed - no floating into the corners etc).
The builder has long since been fired, and the refurb is nearing completion, but, worryingly, some spots of moisture are now starting to appear on the floor of the dining room. I don't know whether it's dampness or the tiles sweating because the liquid DPM is preventing them from breathing. I don't know what to do. There's no money left in the budget to dig the floor up and lay a concrete slab, and I'm worried about laying underlay and carpet on the floor as it is, for fear that both will get damp and mould will follow. I'm considering scraping off the self-levelling screed and applying KA Tanking Slurry, before laying the underlay and carpet. That might work if the moisture I'm seeing is dampness rising from the dirt underneath the tiles, but it would be ineffective and might even worsen the problem if the moisture is due to the tiles sweating.
The carpet fitter's opinion is that the tiles should be able to breathe with underlay and carpet laid on top, but he wasn't sure if the liquid DPM that was poured might prevent them from doing so.
All thoughts and opinions are welcome. I've learnt a lot from this refurb and now realise that floor should have been dug up, but it's not an option at this stage. How best to proceed is the question.
Many thanks in advance.
I'm doing a refurb of an early 1900s terraced house, which has quarry tiles laid on ash in the dining room and kitchen. On reflection, I should have dug the tiles up and laid a concrete slab with a damp proof membrane. This didn't happen unfortunately. I was guided by someone that turned out to be a cowboy builder in the true sense of the phrase, and he assured me that a liquid damp proof treatment over the tiles has been adequate to prevent any dampness coming through on previous homes he has worked on. I didn't know at that time if dampness was indeed rising through the floor as I had only purchased the house a couple of months previous. The tiles were wet when I lifted the laminate floor and fibreboard that was underneath, but that may have been due to sweating. The floor quickly dried out in the days that followed, and there were no signs of dampness over the summer months while the tiles were exposed and the rest of the refurb was progressing.
The builder did pour on a liquid damp proof membrane, followed by a self-levelling screed, the latter being extremely badly applied (it was essentially tipped onto the floor and allowed run to the lowest point, where it congealed - no floating into the corners etc).
The builder has long since been fired, and the refurb is nearing completion, but, worryingly, some spots of moisture are now starting to appear on the floor of the dining room. I don't know whether it's dampness or the tiles sweating because the liquid DPM is preventing them from breathing. I don't know what to do. There's no money left in the budget to dig the floor up and lay a concrete slab, and I'm worried about laying underlay and carpet on the floor as it is, for fear that both will get damp and mould will follow. I'm considering scraping off the self-levelling screed and applying KA Tanking Slurry, before laying the underlay and carpet. That might work if the moisture I'm seeing is dampness rising from the dirt underneath the tiles, but it would be ineffective and might even worsen the problem if the moisture is due to the tiles sweating.
The carpet fitter's opinion is that the tiles should be able to breathe with underlay and carpet laid on top, but he wasn't sure if the liquid DPM that was poured might prevent them from doing so.
All thoughts and opinions are welcome. I've learnt a lot from this refurb and now realise that floor should have been dug up, but it's not an option at this stage. How best to proceed is the question.
Many thanks in advance.
0
Latest MSE News and Guides
Replies
.withdrawal, NOT withdrawel ..bear with me, NOT bare with me
.definitely, NOT definately ......separate, NOT seperate
should have, NOT should of .....guaranteed, NOT guarenteed
Treasure the moments that you have. Savour them for as long as you can for they will never come back again.