We'd like to remind Forumites to please avoid political debate on the Forum... Read More »
We have ‘used’ 600 litres of heating oil in 8 days!
Comments
-
cannugec5 said:matelodave said:You could do what my bro did and install the new tank himselfNever under estimate the power of stupid people in large numbers0
-
cannugec5 said:MikeJXE said:Personally I would have a new temporary over ground pipe fitted rather than go without heatingIt will enable us to use up whatever oil remains in the tank.Initially when I asked if it was possible he wasn’t sure if it would be legal, but has checked up. As long as it is only a temporary solution we can have an over ground pipe.At least that buys us time:)
I doubt it will be a rigid pipe so it should be reasonably flexible
Once he has laid the pipe overground get some young lad to dig it in for you, it doesn't have to be deep 4 inch should be good enough
Out of sight out of mind0 -
MikeJXE said:
Once he has laid the pipe overground get some young lad to dig it in for you, it doesn't have to be deep 4 inch should be good enoughBuried fuel supply pipes
Directly buried fuel supply pipes should be protected against the risk of accidental damage caused by digging. The recommended installation method is as follows:
- A trench should be excavated to a depth of 450mm
- 40mm of compacted sand is laid on the bottom of the trench, the fuel supply pipe positioned, and a further 40mm of compacted sand is laid above the pipe
- Builder’s grade polyethylene is laid above the sand and the trench is then backfilled, positioning fuel supply pipe warning marker tape 150mm below the finished ground level.
Fuel supply pipes should be buried at least 300mm clear of other underground services such as water and electricity. Joints should be avoided in buried pipework, if possible. If joints need to be made, they should be within an inspection chamber.
0 -
lohr500 said:MikeJXE said:
Once he has laid the pipe overground get some young lad to dig it in for you, it doesn't have to be deep 4 inch should be good enoughBuried fuel supply pipes
Directly buried fuel supply pipes should be protected against the risk of accidental damage caused by digging. The recommended installation method is as follows:
- A trench should be excavated to a depth of 450mm
- 40mm of compacted sand is laid on the bottom of the trench, the fuel supply pipe positioned, and a further 40mm of compacted sand is laid above the pipe
- Builder’s grade polyethylene is laid above the sand and the trench is then backfilled, positioning fuel supply pipe warning marker tape 150mm below the finished ground level.
Fuel supply pipes should be buried at least 300mm clear of other underground services such as water and electricity. Joints should be avoided in buried pipework, if possible. If joints need to be made, they should be within an inspection chamber.
Thats the standard for all utility pipes but doesn't mean it always happens
It's a temporary measure until something more permanent can be decided, that could take a week, month or even longer depending on lots of possibilities
0 -
We have finally got a temporary fuel line in. That’s 15 days without our central heating. It felt awful, but I’m well aware that there are very many people worse off.We also had a new “Smart meter” fitted today - except it could not communicate so we have a nice, new, shiny Dumb Meter! I’m not surprised. This is the first time they have ever suggested Smart Meters might work in this area. They don’t!But we are feeling optimistic. We are warm again. We have an Air Source Assessor coming tomorrow to see if our house is suitable for an Air Source Heat Pump and if so we can get it installed ASAP, so that we can continue with our plan to convert the garage into a bedroom.I’m having orthopaedic surgery next month.Would like things sorted first if possible.0
-
So ASHP ASAP? Unless you have a lot of underfloor heating or a lot of free wall space in the vicinity of your existing radiators then I would not trust any assessor who tells you that an ASHP will be cheaper to run than an oil boiler (that is working properly). Then it's really just a matter of whether your existing central heating pipes are large enough in diameter to cope with the higher flow rates that a heat pump uses. And how much it will all cost, of course.Reed0
-
MikeJXE said:lohr500 said:MikeJXE said:
Once he has laid the pipe overground get some young lad to dig it in for you, it doesn't have to be deep 4 inch should be good enoughBuried fuel supply pipes
Directly buried fuel supply pipes should be protected against the risk of accidental damage caused by digging. The recommended installation method is as follows:
- A trench should be excavated to a depth of 450mm
- 40mm of compacted sand is laid on the bottom of the trench, the fuel supply pipe positioned, and a further 40mm of compacted sand is laid above the pipe
- Builder’s grade polyethylene is laid above the sand and the trench is then backfilled, positioning fuel supply pipe warning marker tape 150mm below the finished ground level.
Fuel supply pipes should be buried at least 300mm clear of other underground services such as water and electricity. Joints should be avoided in buried pipework, if possible. If joints need to be made, they should be within an inspection chamber.
Thats the standard for all utility pipes but doesn't mean it always happens
It's a temporary measure until something more permanent can be decided, that could take a week, month or even longer depending on lots of possibilities0 -
MikeJXE said:lohr500 said:MikeJXE said:
Once he has laid the pipe overground get some young lad to dig it in for you, it doesn't have to be deep 4 inch should be good enoughBuried fuel supply pipes
Directly buried fuel supply pipes should be protected against the risk of accidental damage caused by digging. The recommended installation method is as follows:
- A trench should be excavated to a depth of 450mm
- 40mm of compacted sand is laid on the bottom of the trench, the fuel supply pipe positioned, and a further 40mm of compacted sand is laid above the pipe
- Builder’s grade polyethylene is laid above the sand and the trench is then backfilled, positioning fuel supply pipe warning marker tape 150mm below the finished ground level.
Fuel supply pipes should be buried at least 300mm clear of other underground services such as water and electricity. Joints should be avoided in buried pipework, if possible. If joints need to be made, they should be within an inspection chamber.
It's good advice about sand and warning tape. But I'd take the first paragraph as two points .. "Directly buried fuel supply pipes should be protected against the risk of accidental damage caused by digging" That makes sense, they should be protected. Then everything following is just their suggestion how to ensure this. Unless someone can cite actual legislation or case law making this a legal requirement.0 -
Thought it about time I updated this thread. We had the temporary above ground fuel pipe removed in August when the heat pump was installed.3
Confirm your email address to Create Threads and Reply

Categories
- All Categories
- 351K Banking & Borrowing
- 253.1K Reduce Debt & Boost Income
- 453.6K Spending & Discounts
- 244K Work, Benefits & Business
- 598.9K Mortgages, Homes & Bills
- 176.9K Life & Family
- 257.3K Travel & Transport
- 1.5M Hobbies & Leisure
- 16.1K Discuss & Feedback
- 37.6K Read-Only Boards