PLEASE READ BEFORE POSTING: Hello Forumites! In order to help keep the Forum a useful, safe and friendly place for our users, discussions around non-MoneySaving matters are not permitted per the Forum rules. While we understand that mentioning house prices may sometimes be relevant to a user's specific MoneySaving situation, we ask that you please avoid veering into broad, general debates about the market, the economy and politics, as these can unfortunately lead to abusive or hateful behaviour. Threads that are found to have derailed into wider discussions may be removed. Users who repeatedly disregard this may have their Forum account banned. Please also avoid posting personally identifiable information, including links to your own online property listing which may reveal your address. Thank you for your understanding.
The Forum is currently experiencing technical issues which the team are working to resolve. Thank you for your patience.

House not ready on move-in date

Hi

I'm in the process of moving into a new build house. I have an agreed move in date on a signed contract by the builder. I've found out now that it won't be ready in time.

I've arranged to move out of my rented house a couple of days after the new house is finished and booked time off work to move in. Friends and family were all ready to help us move in and now they've told us it won't be ready on time. We're supposed to be moving in next week. It has caused a lot of distress to say the least.

Any advice on this?

Thanks

Comments

  • hamster2013
    hamster2013 Posts: 245 Forumite
    i dont think in my lifetime i have seen a building be completed on a move in date they give many months / year ahead of schedule

    i would never have given my notice in - would have waited until i saw the building complete and the start of finishing touches and even then wait a while to ensure all inside work is complete and only cosmetic touches are left
    i assume your rental was a 1 month notice - so an overlap would have been managable depending on when your mortgage payment is due (always possible to discuss with the bank)

    good luck - your best recourse is your land lord - suggest to him if he can extend your rental and disregard your notice

    he will not be happy as he wants the peace of mind and would rather have someone who would sign for a year or 6 month contract.... but good luck
  • Scope1
    Scope1 Posts: 13 Forumite
    Why do they give completion dates then?

    The builder (quite a large, well known company) is quite embarrassed at the fact that this has run-over and our solicitor is negotiating compensation. To suggest it happens all the time surprises me.

    Are you in the new build business?
  • G_M
    G_M Posts: 51,977 Forumite
    Part of the Furniture 10,000 Posts Name Dropper Combo Breaker
    Most New Build contracts have open Completion dates - usually with some 'end date' ie not later than....

    This allows for delays in the construction eg caused by weather etc.

    However, if you have a fixed Completion date (as is usual with property sales other than New Builds), then your contract will specify the penalties for non-Completion. You should be able to claim a daily % of the purchase price plus your costs.

    Move into a hotel, keep the bills, and claim.
This discussion has been closed.
Meet your Ambassadors

🚀 Getting Started

Hi new member!

Our Getting Started Guide will help you get the most out of the Forum

Categories

  • All Categories
  • 350K Banking & Borrowing
  • 252.7K Reduce Debt & Boost Income
  • 453.1K Spending & Discounts
  • 242.9K Work, Benefits & Business
  • 619.8K Mortgages, Homes & Bills
  • 176.4K Life & Family
  • 255.9K Travel & Transport
  • 1.5M Hobbies & Leisure
  • 16.1K Discuss & Feedback
  • 15.1K Coronavirus Support Boards

Is this how you want to be seen?

We see you are using a default avatar. It takes only a few seconds to pick a picture.