We'd like to remind Forumites to please avoid political debate on the Forum... Read More »
Should I pay building contractor final payment for works which were dragged out?

vraiment
Posts: 20 Forumite
I took on a contractor to carry out a refurb on my buy to let. I signed a professional contract that the works be completed within 5 weeks but in fact the works dragged on for 7 months. The builders were hardly ever on site and impossible to get hold of during the times they were not around. I drip fed the payments and have still kept back the last installment which is several thousands of pounds. As a result of the time scale, I lost a lot of rental revenue. The contractor is demanding the final payment and is refusing to explain why the works took so long. Should I pay the contractor the final payment? Can the contractor sue me for breach of contract?
0
Comments
-
Does the contract provide for liquidated damages?0
-
I will have to have another look at the contract to see if does include liquidated damages. It does include a penalty clause for going over the contract but it amounts to only a few hundred pounds.0
-
-
NO NO NOPE NADA NON under no circumstance pay anything until they have finished, or even better threaten to sue ..... DO NOT PAY ANY MORE and contact trading standards straight away.0
-
I think that if your contract says a penalty clause of say £300 or so than that is what you should hold back however a 5 week job should not run in to 7 months ! unless the builder is taking the p.
Assuming that you are happy with the workmanship and any snagging is complete the builder should be entitled to his final payment minus the £300, unfortunately if that is on the contract as a penalty than I think thats that.
As a tradesman im interested to know what happened after the 5 weeks was up, was the penalty clause discussed then ? best of luck.0 -
I will have to have another look at the contract to see if does include liquidated damages. It does include a penalty clause for going over the contract but it amounts to only a few hundred pounds.
I didn't think contracts could have penalty clauses which is why LAD ( liquidated and ascertained damages) are there. These are an agreed amount for late completion but everyone I've ever seen is £x per week, sometimes with an upper limit in terms of % of contact sum. For example, they could be set at £300 per week with an upper limit of 5% of the contact sum.
are you sure your contact specifies a fixed amount rather than a fixed amount per week?
Either way, if you've lost 5 or 6 months rent then I'd certainty get some legal advice with view to recovering it from the builder.0 -
I took on a contractor to carry out a refurb on my buy to let. I signed a professional contract that the works be completed within 5 weeks but in fact the works dragged on for 7 months. The builders were hardly ever on site and impossible to get hold of during the times they were not around. I drip fed the payments and have still kept back the last installment which is several thousands of pounds.As a result of the time scale, I lost a lot of rental revenue.Should I pay the contractor the final payment?Can the contractor sue me for breach of contract?
You should consult a contract law specialist. You need to be certain of your position.
CheersThe difference between genius and stupidity is that genius has it's limits. - Einstein0 -
fatbikersbouncebetter wrote: »NO NO NOPE NADA NON under no circumstance pay anything until they have finished, or even better threaten to sue ..... DO NOT PAY ANY MORE and contact trading standards straight away.
CheersThe difference between genius and stupidity is that genius has it's limits. - Einstein0 -
IMO it would depend on what part of the work dragged on. If he was building an extension and the part he hadnt finished was putting the roof on then i'd tell him where to go. If however the part not finished was he hadnt put the skirting and coving on id say you should pay the man (minus the £300).0
-
I took on a contractor to carry out a refurb on my buy to let. I signed a professional contract that the works be completed within 5 weeks but in fact the works dragged on for 7 months. The builders were hardly ever on site and impossible to get hold of during the times they were not around.
Legally you are obliged to pay them and yes the contractor can sue you for the payment.
You can obviously counter sue them for lost income if you have enough evidence to prove that they unreasonably delayed doing the work, and you made it clear to them that it was important to complete it within a set time frame.
However I wouldn't bother going to court. Negotiate with the contractor to reduce the amount you should pay, or pay it minus the penalty amount.I'm not cynical I'm realistic
(If a link I give opens pop ups I won't know I don't use windows)0
This discussion has been closed.
Confirm your email address to Create Threads and Reply

Categories
- All Categories
- 349.8K Banking & Borrowing
- 252.6K Reduce Debt & Boost Income
- 453K Spending & Discounts
- 242.7K Work, Benefits & Business
- 619.5K Mortgages, Homes & Bills
- 176.4K Life & Family
- 255.6K Travel & Transport
- 1.5M Hobbies & Leisure
- 16.1K Discuss & Feedback
- 15.1K Coronavirus Support Boards