We’d like to remind Forumites to please avoid political debate on the Forum.

This is to keep it a safe and useful space for MoneySaving discussions. Threads that are – or become – political in nature may be removed in line with the Forum’s rules. Thank you for your understanding.

📨 Have you signed up to the Forum's new Email Digest yet? Get a selection of trending threads sent straight to your inbox daily, weekly or monthly!

Builder asking for too much money upfront for extension and shed builds

Hi all,


Can I please get some advice from you all..


I am doing a single storey extension (extending the existing lounge) with a bath/shower room in the corner on the side and a brick built shed at the back of the garden. I have been quoted £43.5k for the works, which I THINK is reasonable.


Anyway I have narrowed it down to 1 builder, lets call him "Bob". Bob has asked for a third of the amount upfront £14.5k TWO weeks before he has to start (start time is around July end, beginning August). The initial work he has to do is just digging (manually dug, because there is no access for a digger to get through)and drainage I presume. So I said to him, that I am not happy paying so much up front and he said he needs the money to arrange for skips (how expensive are skips these days!) and get the "digging done". He then wants the remaining two thirds of the payments after a month and then second month respectively. I have spoken to a few guys at work and will propose the following payment schedule, does this sound fair to you:




1) Excavation and drainage: 50% up front and remainder after building control have been out and passed it.


2) Footings and damp proofing: 50% up front and remainder after building control have been out and passed it.


3) Brickwork up to plate level and lintels: 50% up front and remainder after building control have been out and passed it.


4) Carpentry, roof, soffits, guttering, soakaway: 50% up front and remainder after completion of this work package.


5) First fix electric and plumbing (wiring and plumbing through walls, ceilings): 50% up front and remainder after completion of this work package.


6) Bonding, plasterboards and skimming: 50% up front and remainder after completion of this work package.


7) Floor screeding: 50% up front and remainder after completion of this work package.


8) Second fix electrics and plumbing (plug sockets, light switches, radiator installation): 50% up front and remainder after completion of this work package.



And 5% of the total price retained until the end of the works for any snagging.




Thank you for your advice in advance.


K
«13456

Comments

  • Doozergirl
    Doozergirl Posts: 34,082 Forumite
    Part of the Furniture 10,000 Posts Name Dropper Photogenic
    No to both. When did you go through your quoting process and agree this start date? I hope it wasn't recently as I'd be amazed for any decent builder to be available that quickly. However, I'd also expect for terms like heavy deposits to be discussed if you'd agreed this start date earlier.

    £14.5 is ridiculous to ask for up front and you've exposed him immediately as his reasoning is poor. A skip is usually in the region of £250. Some skip companies request money up front, most ask when the skip is collected, ime. Perhaps he will hire a digger, which is expensive, but it still doesn't justify that huge amount.

    My gut here is that builders who do this and take large deposits use their clients as an extended credit facility and deposits end up paying to finish other people's jobs. There's a chance that the gravy train ends on your job. The fact that he wants this some time before starting strongly suggests that this is what he does.

    Your own proposal is complicated and still provides plenty of money up front which is completely un-necessary. It's 'bitty', possibly overcomplicated payments and creates admin. On the plus side, you are at least trying to tie payments in with stages. Just lumping a project into three is highly unacceptable, in my view.

    The advice on this board is quite unanimous that payments should be made with agreed regularity based on the % of each element of the project completed. If a builder wants to take a deposit, then there's nothing to say that they can't, but I would draw a limit at 5-10% as a date holder and sign of commitment, with any bespoke orders paid for in advance.
    Everything that is supposed to be in heaven is already here on earth.
  • teneighty
    teneighty Posts: 1,347 Forumite
    edited 5 July 2017 at 11:16AM
    Payment in advance is never a good idea unless the builder needs to order an expensive bespoke item and even then it should be done with great care to ensure ownership of the bespoke item passes to the customer.

    The normal way to arrange payments is to agree a time frame, usually monthly or fortnightly and agreeing a contract valuation of the completed and satisfactory work based on a %. So after first fortnight it could be Foundations 100%, External walls 15%, Ground floor 75% etc etc. Then deduct a small % as a retention if that has been agreed.

    With your version the builder could potentially walk off site half way through the job leaving you substantially out of pocket.

    The vast majority of good honest reliable building contractors do not ask for payment up front.

    As usual Doozer beat me to it with a far more eloquent response.
  • 27cool
    27cool Posts: 267 Forumite
    I would have thought that asking for a lot of money up front is so he can pay off creditors from his existing job. As someone has said. He is using you as a credit provider to keep his business afloat. All this should have been agreed well in advance.(No pun intended)
  • On a project like this, I dont see justification for money up front. Might be he needs to pay somebody else.

    Find a different builder and get a contract.
  • comeandgo
    comeandgo Posts: 5,930 Forumite
    Part of the Furniture 1,000 Posts Name Dropper
    Get a decent company wirh decent credit and experience who can do the first two weeks, get paid on measurement, same the following two weeks and you keep back 10% till everything signed off.
    Why would you be handing a £43.5k contract to a Bob.
  • Dear all, thank you very much for your replies. I will firstly try and tell Bob (again) that there is no way I am paying him 14.5k on three occasions during the project lifecycle. Like many of you have said, I will tell him that I will pay him on measurement of jobs completed as opposed to a lump sum here and there.


    As such no formal contract has been proposed nor put in place. I need to wait for the council to get back to me which will be imminent.


    Thanks again for all your prompt kind advice.


    K
  • Is this the first builder you have approached ? Have you got quotes from others ? Where did you find him?
    Just a few thoughts ;)
  • david1951
    david1951 Posts: 431 Forumite
    Fifth Anniversary Combo Breaker
    A few more thoughts...

    Who is drawing up the contract?
    Who is checking his work at each stage?
    Who is checking his contractors/employees?

    If the answer to the above is yourself, then you need to consider whether you are capable. Building control just check for building regs, they don't check general workmanship or whether the work is being carried out according to the 'contract'. Bob could well take you for a ride and you won't know until it's too late.
  • @another casualty:
    "Is this the first builder you have approached ? Have you got quotes from others ? Where did you find him?
    Just a few thoughts ;) "

    Bob isn't the first builder I approached. I spoke to and obtained almost 5 quotes and found that the average price point was between 43k-47k. Bob was second cheapest, the cheapest builder I was not keen on for a number of reasons. I advertised my job on rated people and he contacted me.


    @david1951
    A few more thoughts...

    Who is drawing up the contract?
    I have not give this any thought to be honest but in the first instance I will approach Bob with my listing of work packages as per my first post.
    Who is checking his work at each stage? No-one is, who can I ask to check the work? Building control only check the first three points of the work packages as per my first post.
    Who is checking his contractors/employees? No-one is, how can I check his employees/contractors? Or is this all a little too much?

    If the answer to the above is yourself, then you need to consider whether you are capable. Building control just check for building regs, they don't check general workmanship or whether the work is being carried out according to the 'contract'. Bob could well take you for a ride and you won't know until it's too late. I understand, I really need to consider whether I will go with Bob now. There is no formal contract in place, not have I provided him with any money to say otherwise.


    Thank you both.
  • Doozergirl
    Doozergirl Posts: 34,082 Forumite
    Part of the Furniture 10,000 Posts Name Dropper Photogenic
    How long have you been speaking to him for?

    We're a little wary of rated people here, as most tradespeople who are any good will have a flow of referral work. We are booked well into next year.

    Those that advertise on rated people are often working on very small works that need a high turnover of clients or, to gve them the benefit of the doubt, they might just be starting out as a contractor. Otherwise, we worry that there is a reason that people doing sizeable jobs like extensions do nit have work already lined up.

    We would really be failing if we needed to take on work a few weeks in advance. It suggests there's nithing going on right now.
    Everything that is supposed to be in heaven is already here on earth.
This discussion has been closed.
Meet your Ambassadors

🚀 Getting Started

Hi new member!

Our Getting Started Guide will help you get the most out of the Forum

Categories

  • All Categories
  • 352.3K Banking & Borrowing
  • 253.6K Reduce Debt & Boost Income
  • 454.3K Spending & Discounts
  • 245.3K Work, Benefits & Business
  • 601.1K Mortgages, Homes & Bills
  • 177.5K Life & Family
  • 259.2K Travel & Transport
  • 1.5M Hobbies & Leisure
  • 16K Discuss & Feedback
  • 37.7K Read-Only Boards

Is this how you want to be seen?

We see you are using a default avatar. It takes only a few seconds to pick a picture.