Moving the bathroom to create 2nd bedroom how much £?

Hello All,
This is my first post so please be patient. I want to convert my 1 bed London flat into a 2 bed to increase the value either for resale or renting out. This means converting the existing bathroom and utility area at the back of the (split level - 7 stairs) flat into a new double bed of approx 10ft sq and moving the bathroom upstairs by using part of existing bedroom and oversized hall. I have drawings and structural calculations so now need a builder. The work needed is as follows;
  • take down partition wall between bedroom and hallway and install wooden beam
  • take down part of stud wall and partition walls from existing bathroom
  • install steel lintel above the new door
  • remove stairs and build new floor and walls for new bathroom
  • build new stairs and storage space under stairs
  • lay new pipes and electric cables to new bathroom
  • remove boiler from existing bathroom and install in a new bathroom above toilet and make nice cabinet to hide boiler
  • tile bathroom and install bathroom equipment
  • install spot lights in new bathroom and extractor fan
  • replace spots in hallway
  • decorate new bedroom
  • run cables for socket and light switches
Plumbing work will cost £4830 inc materials
Electrical work will cost £ 3200 inc materials
Building work will cost £ 7430 inc materials
Total £15460

The job will takes approximately 4 weeks

I will supply bathroom suite, tiles, new boiler if necessary, carpet for new bedroom (and fit) skip plus building control fees etc. The builder is not reg for VAT. He is Polish and I've spoken to a couple of refs who say he is hard working and to a good standard. They both said they trusted him and he was very helpful. I'm convinced neither was a 'plant'. These jobs were however for more standard bathroom refits which he basically did on his own. I think this is a 4 man job over 4/6 weeks. The builder says he has a new team from last year (when he quoted me £3k more!) and can do the work from middle of July.
I still think the price is high although I've had higher quotes....most builders haven't even bothered to get back to me. His quote obviously needs to be broken down better so I can see where any further savings can be made, but am I being unrealistic about the price? This is London!!

Any advice most welcome. Cheers, Blythe58
This discussion has been closed.
★ ★ ★ Meet your Ambassadors

🚀 Getting Started

Hi new member!

Our Getting Started Guide will help you get the most out of the Forum

Categories

  • All Categories
  • 355.9K Banking & Borrowing
  • 255K Reduce Debt & Boost Income
  • 456.2K Spending & Discounts
  • 248.4K Work, Benefits & Business
  • 606.1K Mortgages, Homes & Bills
  • 179.1K Life & Family
  • 264K Travel & Transport
  • 1.5M Hobbies & Leisure
  • 16.2K Discuss & Feedback
  • 37.7K Read-Only Boards
Quick Search

Is this how you want to be seen?

We see you are using a default avatar. It takes only a few seconds to pick a picture.