We'd like to remind Forumites to please avoid political debate on the Forum... Read More »
We're aware that some users are experiencing technical issues which the team are working to resolve. See the Community Noticeboard for more info. Thank you for your patience.
📨 Have you signed up to the Forum's new Email Digest yet? Get a selection of trending threads sent straight to your inbox daily, weekly or monthly!
Some advice please about being forced to move meters
Options
Comments
-
HillStreetBlues said:MWT said:HillStreetBlues said:FreeBear said:Current regulations are not retrospectiveThe usual caveat though is that if there is work required on equipment for other reasons then they have to complete the work to the current standards.
As now no work is needed can they force a meter move even if 2nd engineer was wrong in changing the meters.I don't think that would work as the original problem still remains and it isn't a matter of non-compliance with the current regulations, the problem was the wall should never have been build in a way that separated the fuses from the meters.So there is still a need to correct that in a manner that is compliant with current regulations. The fact that the meters have changed doesn't alter that.
0 -
MWT said:HillStreetBlues said:MWT said:HillStreetBlues said:FreeBear said:Current regulations are not retrospectiveThe usual caveat though is that if there is work required on equipment for other reasons then they have to complete the work to the current standards.
As now no work is needed can they force a meter move even if 2nd engineer was wrong in changing the meters.I don't think that would work as the original problem still remains and it isn't a matter of non-compliance with the current regulations, the problem was the wall should never have been build in a way that separated the fuses from the meters.So there is still a need to correct that in a manner that is compliant with current regulations. The fact that the meters have changed doesn't alter that.
Rereading it it could be a potential safety issue as pointed out by @Qyburn with the cut-out switch but if that's the case it should be the fuse box that is moved not the meter if it complied with the regs when fitted.
As the second engineer didn't have any issues, then it should be checked to see if the first engineer was correct.
Let's Be Careful Out There0 -
OP you've said "meters" but we're mostly talking about electricity. Do you have gas and electricity? Do both meters need moving or just the electricity one? Or do you have more than one electricity meter?Is your incoming electrical supply overhead from a pole, or does it enter your house underground?N. Hampshire, he/him. Octopus Intelligent Go elec & Tracker gas / Vodafone BB / iD mobile. Ripple Kirk Hill member.
2.72kWp PV facing SSW installed Jan 2012. 11 x 247w panels, 3.6kw inverter. 34 MWh generated, long-term average 2.6 Os.Not exactly back from my break, but dipping in and out of the forum.Ofgem cap table, Ofgem cap explainer. Economy 7 cap explainer. Gas vs E7 vs peak elec heating costs, Best kettle!0 -
HillStreetBlues said:MWT said:HillStreetBlues said:MWT said:HillStreetBlues said:FreeBear said:Current regulations are not retrospectiveThe usual caveat though is that if there is work required on equipment for other reasons then they have to complete the work to the current standards.
As now no work is needed can they force a meter move even if 2nd engineer was wrong in changing the meters.I don't think that would work as the original problem still remains and it isn't a matter of non-compliance with the current regulations, the problem was the wall should never have been build in a way that separated the fuses from the meters.So there is still a need to correct that in a manner that is compliant with current regulations. The fact that the meters have changed doesn't alter that.
Rereading it it could be a potential safety issue as pointed out by @Qyburn with the cut-out switch but if that's the case it should be the fuse box that is moved not the meter if it complied with the regs when fitted.
As the second engineer didn't have any issues, then it should be checked to see if the first engineer was correct.
1 -
I had my meter moved 6 years ago and it cost around £1300 plus £300 for the electrician to do all the internal connections. WPD (as was) came and surveyed the property to trace where the power line was (underground) and found their drawings were inaccurate. They dug up a section of my drive to pick up from the power line and installed a new meter on the side of the house - about 4m from the original one that was sited in a store room.I had to supply the external meter box and co-ordinate an electrician to be on-site while the work was completed.£6000 seems a lot of money - have they given you a breakdown of the costs?"Cheap", "Fast", "Right" -- pick two.0
-
As far as I'm aware they need to give a breakdown of the cost, split between "contestible" work that you could arrange yourself using a qualified contractor, and "non contestible" work which only the DNO is allowed to do.1
Confirm your email address to Create Threads and Reply

Categories
- All Categories
- 350.8K Banking & Borrowing
- 253.1K Reduce Debt & Boost Income
- 453.5K Spending & Discounts
- 243.8K Work, Benefits & Business
- 598.7K Mortgages, Homes & Bills
- 176.8K Life & Family
- 257.1K Travel & Transport
- 1.5M Hobbies & Leisure
- 16.1K Discuss & Feedback
- 37.6K Read-Only Boards