Eon not able to install smart meter due to insufficent cable lengths in current install

ccaasjf
ccaasjf Posts: 10 Forumite
First Post

Hiya,

 As part of signing up to 'Eon Next Pledge Tracker' I agreed to have a Smart Meter installed, the install arrived this morning only to tell me that it was impossible to do with my current consumer box wiring due to the fact the cables are too short for them to install one and not sufficient space in the current trunking.

In the last 2 years the whole flat has had a re-wire, the current cable lengths are sufficient for the current install, and I don’t see it as my responsibility to get an electrician back to alter them.

 For example is there any requirements in the current NEICIC regulations that provided direction?

 Any advice is appreciated.

Thank You

Simon


«134

Comments

  • There is a clause in the Electricity Act 1989:

    "The meter shall be installed on the customer’s premises in a position determined by the authorised supplier, unless in all the circumstances it is more reasonable to place it outside those premises or in some other position."

    It goes where they want it.  If your wiring doesn't reach, that's your problem.
  • ccaasjf
    ccaasjf Posts: 10 Forumite
    First Post
    Here is a picture of the current install.
  • p00hsticks
    p00hsticks Posts: 14,257 Forumite
    Part of the Furniture 10,000 Posts Name Dropper Photogenic
    edited 23 April 2024 at 11:00AM

    It goes where they want it.  If your wiring doesn't reach, that's your problem.
    Although I'd argue that if the current meter isn't faulty and the customer has agreed to have a replacement meter fitted but the supplier for whatever reason says they are unable to do so, then the customer should probably still be allowed to stay on the tariff without having the meter replaced unless it's an essential requirement to have a smart meter to operate the tariff (and at first glance that doesn;t seem to be the case for the Eon Next Pledge Tracker... 
  • ccaasjf
    ccaasjf Posts: 10 Forumite
    First Post
    They are saying the following:

    1) The cables are too short running from the consumer box.
    2) For them to use a block to extend them there is insufficent toom in teh trunking to do so.

  • It goes where they want it.  If your wiring doesn't reach, that's your problem.
    Although I'd argue that if the current meter isn't faulty and the customer has agreed to have a replacement meter fitted but the supplier for whatever reason says they are unable to do so, then the customer should probably still be allowed to stay on the tariff without having the meter replaced unless it's an essential requirement to have a smart meter to operate the tariff (and at first glance that doesn;t seem to be the case for the Eon Next Pledge Tracker... 
    Yeah, I'd agree with that.

    ccaasjf said:
    They are saying the following:

    1) The cables are too short running from the consumer box.
    2) For them to use a block to extend them there is insufficent toom in teh trunking to do so.
    I also agree with both of those points.  Looks like an unfortunate consequence of the re-wiring actually being too neat.
  • Chris_b2z
    Chris_b2z Posts: 173 Forumite
    100 Posts First Anniversary Name Dropper
    Surely it must be the supplier's responsibility to find a solution even if it means covering the cost of installing longer meter tails. What will they do when the existing meter fails?
  • doodling
    doodling Posts: 1,231 Forumite
    1,000 Posts Fourth Anniversary Name Dropper
    Hi,
    Chris_b2z said:
    Surely it must be the supplier's responsibility to find a solution even if it means covering the cost of installing longer meter tails. What will they do when the existing meter fails?
    I'm pretty sure that the tails from the meter to the consumer unit belong to the property owner so it is the OPs tails that are too short.

    There is an element of chicken and egg here as an electrician won't deal with the end of the tails that enter the meter whilst the meter installer probably won't want to go messing around in the CU.

    My suggestion would be to get Eon to install an isolator and then get an electrician to wire tails from the isolator to the CU.  You'd need to get your electrician poised to go as you'd be without power between those two steps.

    When the meter installer came to do the work, what did he suggest as the solution?  Would he have been willing to install longer tails to your CU if you had provided the tails, made lots of tea and broken out the good chocolate biscuits?

    As an aside, I assume that the main supply fuse is located elsewhere as I can't see it in the photo?
  • Mister_G
    Mister_G Posts: 1,945 Forumite
    Part of the Furniture 1,000 Posts Name Dropper Combo Breaker
    When Eon came to fit my smart meter a couple of years ago, I asked the fitter to fit an isolator and 25mm flexitails which I supplied.

    For a cup of tea and a few chocolate biscuits it was "no problem"!
  • molerat
    molerat Posts: 34,275 Forumite
    Part of the Furniture 10,000 Posts Name Dropper Photogenic
    Should that screw / disc on the front have a seal on it ?  Did the electrician doing the rewire move the meter ?
  • Zandoni
    Zandoni Posts: 3,465 Forumite
    Part of the Furniture 1,000 Posts Name Dropper Photogenic
    Speak to Eon and see what they say, they may foot the bill.
Meet your Ambassadors

🚀 Getting Started

Hi new member!

Our Getting Started Guide will help you get the most out of the Forum

Categories

  • All Categories
  • 349.9K Banking & Borrowing
  • 252.6K Reduce Debt & Boost Income
  • 453K Spending & Discounts
  • 242.8K Work, Benefits & Business
  • 619.6K Mortgages, Homes & Bills
  • 176.4K Life & Family
  • 255.7K Travel & Transport
  • 1.5M Hobbies & Leisure
  • 16.1K Discuss & Feedback
  • 15.1K Coronavirus Support Boards

Is this how you want to be seen?

We see you are using a default avatar. It takes only a few seconds to pick a picture.