How much does DNO approval cost / is it worth it for my system

Been quoted 8.5k for 

6.4kW of panels over a couple of roof elevations
solaredge 3.68kW inverter 
solar immersion heater thingy
bird barrier

Now I know that the panels are overspecced but believe this is due to two things, they are on different facing roofs and will degrade over time . But I was wondering if its worth upgrading the inverter and going for DNO approval (G99).

Anyone know what it costs to go for G99 compared to G98? Is it worth it

Was going to give battery a miss as its a lot of extra money up front and I am not convinced they pay for themselves
«13

Comments

  • ABrass
    ABrass Posts: 1,005 Forumite
    Part of the Furniture 500 Posts Name Dropper
    That's a silly level of overprovision. Degradation is negligible. In 30 years you'll still be producing 5.2kW at maximum performance. Or 157% of what your inverter can manage.

    I'm not convinced by the solar immersion heaters, they've always seemed to have pretty awful payback periods.

    G99 costs vary by DNO, I think mine does them for free, but there's effort in doing the paperwork. Apparently they're typically 300-500.
    8kW (4kW WNW, 4kW SSE) 6kW inverter. 6.5kWh battery.
  • Martyn1981
    Martyn1981 Posts: 15,245 Forumite
    Part of the Furniture 10,000 Posts Name Dropper Photogenic
    I think you need to go for a bigger export limit.

    Our 5.58kW system is across two roofs with a 180d difference, but still can hold 4.2kW in ideal conditions, and peak and hold close to 5kW for short periods (minute or less). It wouldn't be the end of the World if ours operated across a 3.68kW cap, but still a bit wasteful.

    So, using that as a baseline, I think 6.4kWp would be far too capped at 3.68kW.

    BTW, after 11yrs, I can't detect any noticeable degradation in annual generation, despite originally expecting about 1%pa. Weather differences make direct comparisons YoY tricky, but I suspect any loss we do have, must be less than 5%, perhaps 2 or 3 percent at most.
    Mart. Cardiff. 8.72 kWp PV systems (2.12 SSW 4.6 ESE & 2.0 WNW). 20kWh battery storage. Two A2A units for cleaner heating. Two BEV's for cleaner driving.

    For general PV advice please see the PV FAQ thread on the Green & Ethical Board.
  • ed110220
    ed110220 Posts: 1,541 Forumite
    Part of the Furniture 1,000 Posts Name Dropper Combo Breaker
    Degradation is the least important reason to have as much wattage of panels as possible, as degradation is very slow and most info indicates it is considerably slower than the maximum allowed under the panel's guarantee.

     Much more important is that the more wattage you have, the more you'll be able to cover your consumption on overcast days and especially in the darker part of the year. 

    For example with 4.8 kWp, I'm generating two or three times more than I use (~10 kWh) on sunny or partially sunny days in summer, but only barely covering consumption or even dropping slightly below on the most overcast days. 

    In December I'm only expecting to generate about 3.5 kWh per day on average, less on very overcast days, so little more than a third of my consumption. 

    If I had more panels I could cover more of my winter consumption, but unfortunately I don't have any more suitable roof!

    So ideally you want to squeeze as much panel wattage in as possible I think, especially as our electricity demand is probably going to increase as we switch from using gas to heat pumps for heating. Though there doesn't seem to be an easy rule for working out exactly how much is economically ideal. Ie going so large as to cover the most overcast days in late December is probably not economic, but most people would run into space limitations well before then anyway.
    Solar install June 2022, Bath
    4.8 kW array, Growatt SPH5000 inverter, 1x Seplos Mason 280L V3 battery 15.2 kWh.
    SSW roof. ~22° pitch, BISF house. 12 x 400W Hyundai panels
  • ispookie666
    ispookie666 Posts: 1,194 Forumite
    Part of the Furniture 1,000 Posts Name Dropper Combo Breaker
    Probably around 250. It's a bit of faff. The G98 is only export limitation. These are the options 
    1. G99 
    2. Reduce the array size to 4KWpwith a view to add additional panels and battery at a later stage along with DNO approval. 
    3. Get a bigger size inverter and limit to 3.68KWp export. 
    “Don't raise your voice, improve your argument." - Desmond Tutu

    System 1 - 14 x 250W SunModule SW + Enphase ME215 microinverters (July 2015)
    System 2 - 9.2 KWp + Enphase IQ7+ and IQ8AC (Feb 22 & Sep 24) + Givenergy AC Coupled inverter + 2 * 8.2KWh Battery (May 2022) + Mitsubishi 7.1 KW and 2* Daikin 2.5 KW A2A Heat Pump
  • Spies
    Spies Posts: 2,248 Forumite
    Part of the Furniture 1,000 Posts Photogenic Name Dropper
    I think the 2nd option that @ispookie666 suggests will be best.
    4.29kWp Solar system, 45/55 South/West split in cloudy rainy Cumbria. 
  • ccbrowning
    ccbrowning Posts: 431 Forumite
    Part of the Furniture 100 Posts Name Dropper
    Is there a range? I spoke to an installer who told me to speak to the DNO first and it could be up to £9k, to go over 3.68kW. I have an existing 3.4kW system and want to expand and add a battery.

    Can you just get an inverter that limits export?
    https://www.enwl.co.uk/get-connected/apply-for-a-new-connection/generation-and-storage/micro-generation-and-storage-connections/

    Integrated micro-generation and storage

    Working in partnership with the ENA, a relaxation was written into G99. This relaxation has primarily been developed where a customer is wishing to combine a G83/G98 generator with an Energy Storage Device.

    To qualify, the following conditions must be met:

    • Total generation capacity installed should not exceed 7.36KW (including battery storage)
    • All generators should be connected via a Type approved G83/G98 protection device
    • The maximum export should be limited to 3.68KW per phase utilising a Type approved EREC G100 device
    • The system should not generate during a power-cut (island mode) 
  • Hexane
    Hexane Posts: 522 Forumite
    Sixth Anniversary 500 Posts Name Dropper
    I would definitely seek DNO approval. They might agree with a small fee, they might agree without a fee, they might flat out say no, they might quote you a fee of thousands for approval. My DNO initially asked for a £1500 fee, then later agreed to our proposal without a fee.

    It really doesn't seem worth limiting your generation (or even your export) by so much, if there's a way round it.
    7.25 kWp PV system (4.1kW WSW & 3.15kW ENE), Solis inverter, myenergi eddi & harvi for energy diversion to immersion heater. myenergi hub for Virtual Power Plant demand-side response trial.
  • ccbrowning
    ccbrowning Posts: 431 Forumite
    Part of the Furniture 100 Posts Name Dropper
    Hexane said:
    I would definitely seek DNO approval. They might agree with a small fee, they might agree without a fee, they might flat out say no, they might quote you a fee of thousands for approval. My DNO initially asked for a £1500 fee, then later agreed to our proposal without a fee.

    It really doesn't seem worth limiting your generation (or even your export) by so much, if there's a way round it.
    I see - well that is one installer who is out of the picture, since they wanted me to find out first? One out of Yorkshire.
  • ABrass
    ABrass Posts: 1,005 Forumite
    Part of the Furniture 500 Posts Name Dropper
    Is there a range? I spoke to an installer who told me to speak to the DNO first and it could be up to £9k, to go over 3.68kW. I have an existing 3.4kW system and want to expand and add a battery.

    Can you just get an inverter that limits export?
    https://www.enwl.co.uk/get-connected/apply-for-a-new-connection/generation-and-storage/micro-generation-and-storage-connections/

    Integrated micro-generation and storage

    Working in partnership with the ENA, a relaxation was written into G99. This relaxation has primarily been developed where a customer is wishing to combine a G83/G98 generator with an Energy Storage Device.

    To qualify, the following conditions must be met:

    • Total generation capacity installed should not exceed 7.36KW (including battery storage)
    • All generators should be connected via a Type approved G83/G98 protection device
    • The maximum export should be limited to 3.68KW per phase utilising a Type approved EREC G100 device
    • The system should not generate during a power-cut (island mode) 
    The only reason it might cost £9k is if you need to install 3 phase power. And that seems like an expensive quote for that.

    Many modern inverters can cap export, it's a common feature now.
    8kW (4kW WNW, 4kW SSE) 6kW inverter. 6.5kWh battery.
  • ispookie666
    ispookie666 Posts: 1,194 Forumite
    Part of the Furniture 1,000 Posts Name Dropper Combo Breaker
    @ccbrowning Export limitation becomes a G100, your DNO can play hard ball and would want to do a site visit to check if the export limit is met.  For a few inverters, export limitation is just a software mod/profile.  
    The cost for DNo approval would depend on a lot of things - your total house current input, high ampere devices, local grid capacity, age of the supply lines etc. 
    You could always call the DNO and check.  I did contact my DNO a few years ago for a Inverter battery install(DIY self install). They were very accomodating and mentioned to get inverter which were already certified/tested so that site visit was not needed.  
    “Don't raise your voice, improve your argument." - Desmond Tutu

    System 1 - 14 x 250W SunModule SW + Enphase ME215 microinverters (July 2015)
    System 2 - 9.2 KWp + Enphase IQ7+ and IQ8AC (Feb 22 & Sep 24) + Givenergy AC Coupled inverter + 2 * 8.2KWh Battery (May 2022) + Mitsubishi 7.1 KW and 2* Daikin 2.5 KW A2A Heat Pump
Meet your Ambassadors

🚀 Getting Started

Hi new member!

Our Getting Started Guide will help you get the most out of the Forum

Categories

  • All Categories
  • 350K Banking & Borrowing
  • 252.7K Reduce Debt & Boost Income
  • 453.1K Spending & Discounts
  • 242.9K Work, Benefits & Business
  • 619.8K Mortgages, Homes & Bills
  • 176.4K Life & Family
  • 255.9K Travel & Transport
  • 1.5M Hobbies & Leisure
  • 16.1K Discuss & Feedback
  • 15.1K Coronavirus Support Boards

Is this how you want to be seen?

We see you are using a default avatar. It takes only a few seconds to pick a picture.