We'd like to remind Forumites to please avoid political debate on the Forum... Read More »
📨 Have you signed up to the Forum's new Email Digest yet? Get a selection of trending threads sent straight to your inbox daily, weekly or monthly!
Solar Power - Definitely Green but is it affordable
Options
Comments
-
Fitting a 100l tank in the loft just for a shower would be better than a electric shower, Maybe 2 valves on the pipes so you can switch over to combi heated water in winter.
0 -
007apm said:As was the guidance from many forums and web articles, it is a good idea to monitor the meters for the first few weeks to make sure nothing is amiss. I have however found a likely fault in the installation. We have 2 fuse boxes, one for upstairs and one for downstairs. The downstairs fuse box has a new fuse for 'Solar' but the upstairs one has not been changed. Given that we have some TVs, a games console and some hair dryers upstairs, I am hoping that connecting upstairs to solar will then use the battery / direct solar feed and reduce our grid dependency even further and save on grid imports! I'm expecting the engineer tomorrow and will report back in a few days.If you have a typical UK single phase supply, with both consumer units being fed off the same meter, then that will be fine. The solar power will make its way to wherever it's needed.It won't be so good if you have a three-phase supply, or separate meters for each consumer unit.Note sure if it's a single phase or three phase? Count the wires going to the meter. Two wires in and two wires out is single phase. Four wires in and four wires out is three phase (three lives and a neutral).If it sticks, force it.
If it breaks, well it wasn't working right anyway.0 -
If it is of any interest our 6KWh system generated above expectation and there were only 3 days where grid use was significant.
June Week Day KWh Total Average Min Max Used 314.7 10.49 6.3 18.3 Grid 19 0.633 0 4.3 Generated 777.4 25.91 6.6 39.2 SEG 481.7 16.06 0 32.2
In June unfortunately we are still unable to claim SEG due to a lack of a DNO. I chased this with UK Power Networks only to be advised that a DNO should have been in place before installation (>3.68KWhP) and they had no record of an application. Our installer is on the case but it looks like a 'Schoolboy/Schoolgirl error to me!' :-(0 -
How much are you taking from the batteries over night currently, any charts? 20% or more like 80%?
Time to get a hot tub?0 -
007apm said:If it is of any interest our 6KWh system generated above expectation and there were only 3 days where grid use was significant.
June Week Day KWh Total Average Min Max Used 314.7 10.49 6.3 18.3 Grid 19 0.633 0 4.3 Generated 777.4 25.91 6.6 39.2 SEG 481.7 16.06 0 32.2
In June unfortunately we are still unable to claim SEG due to a lack of a DNO. I chased this with UK Power Networks only to be advised that a DNO should have been in place before installation (>3.68KWhP) and they had no record of an application. Our installer is on the case but it looks like a 'Schoolboy/Schoolgirl error to me!' :-(
For the purposes of a G99 Application, the battery inverter is treated as a potential exporter to the Grid. It follows for a 6.5kWp array and a 5kW battery, the total export value could be as high as11.5kW.
The DNO will then decide whether to impose a site export limit which may be considerably less than you would hope for. I have seen reports of some large arrays with batteries being limited to 16 amps/per phase or 3.68kW on a single phase supply because the local Grid infrastructure was incapable of taking the load. This has to be managed by a restriction on the inverter.
Once the installation is complete, the installer is supposed to run commissioning tests and provide these results to the DNO. This includes such things as how quickly the solar inverter shuts down post a Grid failure. The DNO will assess these tests and sign off on the installation. It is this DNO sign off that suppliers like Octopus want to see before applying to the DNO for an export MPAN for your meter. DNOs reserve the right to carry out their own post-installation Witness Testing at cost to the homeowner.
https://www.ukpowernetworks.co.uk/electricity/distribution-energy-resources/installing-large-scale-distributed-generation
0 -
markin said:How much are you taking from the batteries over night currently, any charts? 20% or more like 80%?
Time to get a hot tub?10-19 20-29 30-39 40-49 50-59 60-69 70-79 80-89 90-99 10.4% 4.5% 17.9% 19.4% 25.4% 11.9% 9.0% 0.0% 1.5%
This chart shows the battery remaining each morning as percentages. The system won't drop below 10%. Plan is to increase the capacity from 7.2KWh to 13Kwh in a month or so.
No idea how much energy it takes to heat a hot tub! Enjoy...1
Confirm your email address to Create Threads and Reply

Categories
- All Categories
- 351.1K Banking & Borrowing
- 253.1K Reduce Debt & Boost Income
- 453.6K Spending & Discounts
- 244.1K Work, Benefits & Business
- 599K Mortgages, Homes & Bills
- 177K Life & Family
- 257.4K Travel & Transport
- 1.5M Hobbies & Leisure
- 16.1K Discuss & Feedback
- 37.6K Read-Only Boards