We'd like to remind Forumites to please avoid political debate on the Forum... Read More »
We're aware that some users are experiencing technical issues which the team are working to resolve. See the Community Noticeboard for more info. Thank you for your patience.
📨 Have you signed up to the Forum's new Email Digest yet? Get a selection of trending threads sent straight to your inbox daily, weekly or monthly!
Part of work completed before Planning approval
Options

ispookie666
Posts: 1,194 Forumite


My original plan was to install 3x air conditioning units (air to air heat pump) after nearly running out of oil at the peak of winter with the added benefit of cooling. I had already run this past my neighbours and these outdoor units are not going to be visible from their property, and our house is pretty much next to a road and is noisy.
Closer to the time of install I realised the need for Planning permission as these would not be considered as permitted development! Interestingly, the few cooling contractors who provided the quote had no idea about this.
I duly completed the form, added the required documents and had marked the section "has work already started as -NO"
As I heard nothing for 3 weeks, I jumped the gun and asked the contractor to go ahead with the install.
I installed 2 of these units - smaller ones (each is 2.5KW) as per the drawings submitted. I have held off the bigger 7.1KW unit (will be installed by a different contractor).
Now two weeks later, the councils planning have finally validated my application (after submission of elevation) and have said, they would need to do a site visit.
I have no idea what to do, should I contact them and say - I have done the partial install or just wait for them to do the site visit?
I have posted this same on another forum, I hope there is more traffic here - thanks in advance
Closer to the time of install I realised the need for Planning permission as these would not be considered as permitted development! Interestingly, the few cooling contractors who provided the quote had no idea about this.
I duly completed the form, added the required documents and had marked the section "has work already started as -NO"
As I heard nothing for 3 weeks, I jumped the gun and asked the contractor to go ahead with the install.
I installed 2 of these units - smaller ones (each is 2.5KW) as per the drawings submitted. I have held off the bigger 7.1KW unit (will be installed by a different contractor).
Now two weeks later, the councils planning have finally validated my application (after submission of elevation) and have said, they would need to do a site visit.
I have no idea what to do, should I contact them and say - I have done the partial install or just wait for them to do the site visit?
I have posted this same on another forum, I hope there is more traffic here - thanks in advance
“Don't raise your voice, improve your argument." - Desmond Tutu
System 1 - 14 x 250W SunModule SW + Enphase ME215 microinverters (July 2015)
System 2 - 9.2 KWp + Enphase IQ7+ and IQ8AC (Feb 22 & Sep 24) + Givenergy AC Coupled inverter + 2 * 8.2KWh Battery (May 2022) + Mitsubishi 7.1 KW and 2* Daikin 2.5 KW A2A Heat Pump
System 1 - 14 x 250W SunModule SW + Enphase ME215 microinverters (July 2015)
System 2 - 9.2 KWp + Enphase IQ7+ and IQ8AC (Feb 22 & Sep 24) + Givenergy AC Coupled inverter + 2 * 8.2KWh Battery (May 2022) + Mitsubishi 7.1 KW and 2* Daikin 2.5 KW A2A Heat Pump
0
Comments
-
Technically you have submitted the wrong type of application. So they will ask you to withdraw and resubmit unfortunately.
It doesnt mean the council with take issue with what you have done but it is a procedural thing where they can not approve something that has already been implemented. Ticking 'yes' to that question completely changes the type of application that gets submitted.
You could try your luck and say that you are shielding or something but can provide photos. Then send some old ones. Most of the local councils near me are still not visiting and relying on photos.1 -
Ignore @Newuser1987 as it’s nothing to do with the ‘type’ of application.
What you @ispookie666 have done is correct because at the time the application was submitted, works had not commenced. When Planning come to carry out their visit, they will obviously see works have started. They may choose to re-word the description of the proposal to include the term ‘part retrospective’ or they’ll just include a note when they come to write up their report/assessment.
Don’t go to the hassle of getting in contact with prior to the visit. If you happen to see them at the time of the visit, mention it then. If your LPA is like the ones around here, they are still wanting to carry out visits unaccompanied.2 -
To avoid delay with planners needing to reconsult I would inform them that the application is now part retrospective. Have you carried our noise reports or were you told you don't need these?1
-
Did they say site visit BEFORE commencement? Perhaps they want to visit post installation."A nation's greatness is measured by how it treats its weakest members." ~ Mahatma Gandhi
Ride hard or stay home :iloveyou:1 -
I'm not familiar with planning terminology, what does 'validated my application' mean? That they acknowledge receipt? or something more than that.The fact that the neighbours haven't raised any objection doesn't automatically mean the council will approve.1
-
To validate it means that they have checked all paperwork that was needed has been submitted correctly and they've entered it into the system, starting the clock ticking on the expected decision date.Everything that is supposed to be in heaven is already here on earth.
2 -
Thanks Doozergirl.
1 -
DevilDamo said:Ignore @Newuser1987 as it’s nothing to do with the ‘type’ of application.
What you @ispookie666 have done is correct because at the time the application was submitted, works had not commenced. When Planning come to carry out their visit, they will obviously see works have started. They may choose to re-word the description of the proposal to include the term ‘part retrospective’ or they’ll just include a note when they come to write up their report/assessment.
Don’t go to the hassle of getting in contact with prior to the visit. If you happen to see them at the time of the visit, mention it then. If your LPA is like the ones around here, they are still wanting to carry out visits unaccompanied.
There are 'types' of applications. Refer to the Town and Country Planning Act 1990. A Section 73A application needs to be submitted for restrospective applications.
I think generally you are unlikely to have an issue but I believe from my experience and planning law the case officer may not determine the application if they spot works have started/completed. Anyone could apply and tick 'no' works hadnt started and then claim it was done since the application was made. How would a case officer ever know otherwise.1 -
"As part of the assessment stage I will need to visit the site. You do not need to be present during
this visit however I may contact you if the site is inaccessible or access is restricted." These are the exact wordings.
I presume the date of application and then the date of starting the work would help in showing that at the time of application, work had not started. According to their website, it seems to be 4 days for validation from the submission date, as I had not heard anything for nearly 3 weeks - I decided to go ahead.
I think i'll wait.
“Don't raise your voice, improve your argument." - Desmond Tutu
System 1 - 14 x 250W SunModule SW + Enphase ME215 microinverters (July 2015)
System 2 - 9.2 KWp + Enphase IQ7+ and IQ8AC (Feb 22 & Sep 24) + Givenergy AC Coupled inverter + 2 * 8.2KWh Battery (May 2022) + Mitsubishi 7.1 KW and 2* Daikin 2.5 KW A2A Heat Pump0 -
Newuser1987 said:DevilDamo said:Ignore @Newuser1987 as it’s nothing to do with the ‘type’ of application.
What you @ispookie666 have done is correct because at the time the application was submitted, works had not commenced. When Planning come to carry out their visit, they will obviously see works have started. They may choose to re-word the description of the proposal to include the term ‘part retrospective’ or they’ll just include a note when they come to write up their report/assessment.
Don’t go to the hassle of getting in contact with prior to the visit. If you happen to see them at the time of the visit, mention it then. If your LPA is like the ones around here, they are still wanting to carry out visits unaccompanied.
There are 'types' of applications. Refer to the Town and Country Planning Act 1990. A Section 73A application needs to be submitted for restrospective applications.
I think generally you are unlikely to have an issue but I believe from my experience and planning law the case officer may not determine the application if they spot works have started/completed. Anyone could apply and tick 'no' works hadnt started and then claim it was done since the application was made. How would a case officer ever know otherwise.
1
Confirm your email address to Create Threads and Reply

Categories
- All Categories
- 351K Banking & Borrowing
- 253.1K Reduce Debt & Boost Income
- 453.6K Spending & Discounts
- 244K Work, Benefits & Business
- 598.9K Mortgages, Homes & Bills
- 176.9K Life & Family
- 257.3K Travel & Transport
- 1.5M Hobbies & Leisure
- 16.1K Discuss & Feedback
- 37.6K Read-Only Boards