Thames Water Build over agreement How long?

TheEffects
Posts: 150 Forumite


Hi
I am looking to do extension, there is currently a manhole in the way that requires removing.
I have seen the application form on the water company website.
Does anyone have a time frame, as to the length it will take from approval prospective.
Or is it similar to building control, you can start after 48 hours?
Regards
The effects.
I am looking to do extension, there is currently a manhole in the way that requires removing.
I have seen the application form on the water company website.
Does anyone have a time frame, as to the length it will take from approval prospective.
Or is it similar to building control, you can start after 48 hours?
Regards
The effects.
0
Comments
-
Thames water are normally very efficient with their build over applications.
I would say on average it takes 8-10 days to get approval. That is with the assumption that you provide them with all the necessary drawings.0 -
in some instances TW will allow you to self certify your works. take a look at their website for the criteria.
I went this route, worked out cheaper and was approved within a week.0
This discussion has been closed.
Confirm your email address to Create Threads and Reply

Categories
- All Categories
- 351.7K Banking & Borrowing
- 253.4K Reduce Debt & Boost Income
- 454K Spending & Discounts
- 244.7K Work, Benefits & Business
- 600.1K Mortgages, Homes & Bills
- 177.3K Life & Family
- 258.4K Travel & Transport
- 1.5M Hobbies & Leisure
- 16.2K Discuss & Feedback
- 37.6K Read-Only Boards