Thames Water Build over agreement How long?
Options

TheEffects
Posts: 150 Forumite


Hi
I am looking to do extension, there is currently a manhole in the way that requires removing.
I have seen the application form on the water company website.
Does anyone have a time frame, as to the length it will take from approval prospective.
Or is it similar to building control, you can start after 48 hours?
Regards
The effects.
I am looking to do extension, there is currently a manhole in the way that requires removing.
I have seen the application form on the water company website.
Does anyone have a time frame, as to the length it will take from approval prospective.
Or is it similar to building control, you can start after 48 hours?
Regards
The effects.
0
Comments
-
Hi,
I submitted a build over application form in June due to the same issue - manhole in the way of our extension! It was a really simple process, and I seem to remember it taking around a week from form submission to approval.SPC # 1150
This discussion has been closed.
Confirm your email address to Create Threads and Reply

Categories
- All Categories
- 351.1K Banking & Borrowing
- 253.2K Reduce Debt & Boost Income
- 453.6K Spending & Discounts
- 244.1K Work, Benefits & Business
- 599.1K Mortgages, Homes & Bills
- 177K Life & Family
- 257.5K Travel & Transport
- 1.5M Hobbies & Leisure
- 16.1K Discuss & Feedback
- 37.6K Read-Only Boards