Contractor vs construction engineer

Hi all,

I have got a construction engineer to do the calculations to support my chimney in loft while removing it from the first and second floor

Engineer charged me a decent sum and gave me a drawing which shows the model and type of still which should be used however not the legnth of the steel

Contractor is saying that is not my job and it should be on the drawing from engineers and vice versa

Do engineers need to specify the exact legnth of any beam etc?

Comments

  • Doozergirl
    Doozergirl Posts: 34,082 Forumite
    Part of the Furniture 10,000 Posts Name Dropper Photogenic
    Our structural engineer doesn't put the length. I presume because the opening isn't exactly set until it's made and they can't be responsible for the builder's size of opening.

    Building regs require a certain depth of overhang to comply so it's easy to work out if you know what you're doing.
    Everything that is supposed to be in heaven is already here on earth.
  • System
    System Posts: 178,483 Community Admin
    10,000 Posts Photogenic Name Dropper
    where you are doing alterations beams are generally site sized - the engineer should have a minimum bearing distance (usually 150mm) for the beam but the length would measured by the contractor on site
    This is a system account and does not represent a real person. To contact the Forum Team email forumteam@moneysavingexpert.com
  • So are are they just removing first/ second floor of chimney breast but leaving below and above that’s a strange way to do it ?
  • teneighty
    teneighty Posts: 1,347 Forumite
    The structural engineer should have specified the "span" of the beam to do his calculations. The builder then just has to add the span (width of opening) and the end bearings to get the overall length.

    It sounds like the engineer has not provided a copy of the calculations which you will need to submit to Building Control.
  • Mocha61
    Mocha61 Posts: 107 Forumite
    My daughter had this work done last year,the structural engineer did not advice the length of the rsj, he said this was for the builder to calculate, seems its normal practice.
This discussion has been closed.
★ ★ ★ Meet your Ambassadors

🚀 Getting Started

Hi new member!

Our Getting Started Guide will help you get the most out of the Forum

Categories

  • All Categories
  • 355.6K Banking & Borrowing
  • 254.8K Reduce Debt & Boost Income
  • 456.1K Spending & Discounts
  • 248.2K Work, Benefits & Business
  • 605.7K Mortgages, Homes & Bills
  • 179K Life & Family
  • 263.5K Travel & Transport
  • 1.5M Hobbies & Leisure
  • 16.1K Discuss & Feedback
  • 37.7K Read-Only Boards

Is this how you want to be seen?

We see you are using a default avatar. It takes only a few seconds to pick a picture.