PLEASE READ BEFORE POSTING: Hello Forumites! In order to help keep the Forum a useful, safe and friendly place for our users, discussions around non-MoneySaving matters are not permitted per the Forum rules. While we understand that mentioning house prices may sometimes be relevant to a user's specific MoneySaving situation, we ask that you please avoid veering into broad, general debates about the market, the economy and politics, as these can unfortunately lead to abusive or hateful behaviour. Threads that are found to have derailed into wider discussions may be removed. Users who repeatedly disregard this may have their Forum account banned. Please also avoid posting personally identifiable information, including links to your own online property listing which may reveal your address. Thank you for your understanding.
📨 Have you signed up to the Forum's new Email Digest yet? Get a selection of trending threads sent straight to your inbox daily, weekly or monthly!

Contractor looking for more money

In June we agreed an estimate with a contractor to carry out an extension and some renovation works to our new property at a cost for labour only. It was agreed that it would be completed with a reasonable time to allow us to decorate etc before Christmas.

Due to extras being charged for and the time taking to complete these extra, this finishing time will not happen. This is not the issue though.

I asked him to provide a cost of how much he would want for having carried out extra / unforeseen works. He has provided this and I have no issue with it as in my opinion it will compensate him for the time lost not working on the original quotation.

However he has sent another bill through asking for £5000.00 extra to complete the original quotation of works. This is exactly 25% increase on the original price. I had expected to pay a little extra and had agreed in principle that we would do so. In my budget I expected this to be £1000.00 at the maximum.

He has already said that he underestimated our job by like £5000.00. However it seems like he is expecting us to bear the entire responsibility for him underestimating the job. I work in the web industry and would never think of asking a customer to stump up more money for work I had quoted for, just because I had messed up my numbers.


I guess I am looking for advice or suggestions.

Thanks very much in advance.

Comments

  • RAS
    RAS Posts: 37,042
    Part of the Furniture 10,000 Posts Name Dropper
    Forumite
    If he provided an estimate you do not have a leg to stand on really.

    If he provided a quotation, then there is a basis for discussion.
    If you've have not made a mistake, you've made nothing
  • Try the DIY board a bit further down (In the Home or something it's called) as well as here. They have a whole section for dealing with trades quotes etc.
  • Tyler119
    Tyler119 Posts: 341 Forumite
    RAS wrote: »
    If he provided an estimate you do not have a leg to stand on really.

    If he provided a quotation, then there is a basis for discussion.

    Ive had the paperwork and he has listed what works will be carried out and then put:

    Price: £20,000.00 labour only
  • Tyler119
    Tyler119 Posts: 341 Forumite
    Try the DIY board a bit further down (In the Home or something it's called) as well as here. They have a whole section for dealing with trades quotes etc.

    Thank you, will do.
  • nidO
    nidO Posts: 847 Forumite
    You can maybe ask him if there's any way he'd be willing to split the difference, but it's important to note that a quote is not the same thing as an estimate.
    If he gave you a quote to complete the works outlined at a set price then you can argue the case with him to stick to his quote as that's the whole purpose of a quote, however if he gave you an estimate then by its very nature it can change.

    My approach would be to ask for a breakdown of the additional previously underestimated work to try to determine whether the additional time/effort/labour needed is something he would have had no reasonable way to know when providing the original quote, or whether it's additional work he should reasonably have been able to see would be needed.
    Anything that then falls into the latter category, ask him to knock off.
  • Tyler119
    Tyler119 Posts: 341 Forumite
    nidO wrote: »
    You can maybe ask him if there's any way he'd be willing to split the difference, but it's important to note that a quote is not the same thing as an estimate.
    If he gave you a quote to complete the works outlined at a set price then you can argue the case with him to stick to his quote as that's the whole purpose of a quote, however if he gave you an estimate then by its very nature it can change.

    My approach would be to ask for a breakdown of the additional previously underestimated work to try to determine whether the additional time/effort/labour needed is something he would have had no reasonable way to know when providing the original quote, or whether it's additional work he should reasonably have been able to see would be needed.
    Anything that then falls into the latter category, ask him to knock off.

    I guess my issue is that he is saying because of extra works carried out that the original quotation of works will take longer. However I am paying him for the extra works and so he shouldn't be out of pocket. Except he is asking 25% extra of the original price to complete the work, because he got his numbers wrong.
  • RAS wrote: »
    If he provided an estimate you do not have a leg to stand on really.

    If he provided a quotation, then there is a basis for discussion.

    IIRC

    ball park = +- 35%
    estimate = +- 15%
    Quote = +-0%
  • Tyler119
    Tyler119 Posts: 341 Forumite
    IIRC

    ball park = +- 35%
    estimate = +- 15%
    Quote = +-0%

    Thats what I thought, I budgeted for around 10% to 15% for any extra work that came along, which around what his bill for extra work will come to.

    We were willing to pay him a little extra on top of this to be reasonable, however I think he is being very unreasonable asking for 25% extra.
  • Did you sign a contract? Or did you draw up a contract?
    An opinion is just that..... An opinion
This discussion has been closed.
★ ★ ★ Meet your Ambassadors

🚀 Getting Started

Hi new member!

Our Getting Started Guide will help you get the most out of the Forum

Categories

  • All Categories
  • 355.7K Banking & Borrowing
  • 254.9K Reduce Debt & Boost Income
  • 456.1K Spending & Discounts
  • 248.3K Work, Benefits & Business
  • 605.9K Mortgages, Homes & Bills
  • 179K Life & Family
  • 263.7K Travel & Transport
  • 1.5M Hobbies & Leisure
  • 16.2K Discuss & Feedback
  • 37.7K Read-Only Boards

Is this how you want to be seen?

We see you are using a default avatar. It takes only a few seconds to pick a picture.