order of modernisation works

We'll be hopefully buying a house soon that needs a lot of modernisation & general updating.

I've just realised that I have absolutely no idea in which order to get things done :o We would need to get pretty much everything sorted, so plumbing, central heating, electrics, boiler re-sited, plastering and ceilings.

Would any kind soul have any advice on how to approach this daunting list? I keep going round in circles thinking that we can't do the plastering until the plumbing is done, but we also can't do the plumbing until the boiler is re-sited which requires the plastering......!
"Science is a wonderful thing if one does not have to earn one's living at it" Einstein 1951

Comments

  • Mankysteve
    Mankysteve Posts: 4,257 Forumite
    Part of the Furniture 1,000 Posts Combo Breaker
    edited 7 May 2011 at 1:13PM
    Well for the boiler you decided the site put in the piping and electric supply then the plaster then put in the boiler.
  • Grimbal
    Grimbal Posts: 2,334 Forumite
    Part of the Furniture Combo Breaker
    and for the whole house? Does the plumbing get done first, then the CH, electrics & plastering always last?
    "Science is a wonderful thing if one does not have to earn one's living at it" Einstein 1951
  • Canucklehead
    Canucklehead Posts: 6,254 Forumite
    Good afternoon: see here.

    HTH

    Canucklehead
    Ask to see CIPHE (Chartered Institute of Plumbing & Heating Engineering)
  • Grimbal
    Grimbal Posts: 2,334 Forumite
    Part of the Furniture Combo Breaker
    thankyou so much - very useful!
    "Science is a wonderful thing if one does not have to earn one's living at it" Einstein 1951
  • Mankysteve
    Mankysteve Posts: 4,257 Forumite
    Part of the Furniture 1,000 Posts Combo Breaker
    edited 7 May 2011 at 3:26PM
    1.Pipe work first fix
    2.Electrics first fix
    3.Plaster
    4.electric second fix
    5.boiler installation.
    6.Plumbing Second fix
This discussion has been closed.
Meet your Ambassadors

🚀 Getting Started

Hi new member!

Our Getting Started Guide will help you get the most out of the Forum

Categories

  • All Categories
  • 352.5K Banking & Borrowing
  • 253.7K Reduce Debt & Boost Income
  • 454.5K Spending & Discounts
  • 245.5K Work, Benefits & Business
  • 601.4K Mortgages, Homes & Bills
  • 177.6K Life & Family
  • 259.4K Travel & Transport
  • 1.5M Hobbies & Leisure
  • 16K Discuss & Feedback
  • 37.7K Read-Only Boards

Is this how you want to be seen?

We see you are using a default avatar. It takes only a few seconds to pick a picture.