order of modernisation works
Grimbal
Posts: 2,334 Forumite
We'll be hopefully buying a house soon that needs a lot of modernisation & general updating.
I've just realised that I have absolutely no idea in which order to get things done
We would need to get pretty much everything sorted, so plumbing, central heating, electrics, boiler re-sited, plastering and ceilings.
Would any kind soul have any advice on how to approach this daunting list? I keep going round in circles thinking that we can't do the plastering until the plumbing is done, but we also can't do the plumbing until the boiler is re-sited which requires the plastering......!
I've just realised that I have absolutely no idea in which order to get things done
Would any kind soul have any advice on how to approach this daunting list? I keep going round in circles thinking that we can't do the plastering until the plumbing is done, but we also can't do the plumbing until the boiler is re-sited which requires the plastering......!
"Science is a wonderful thing if one does not have to earn one's living at it" Einstein 1951
0
Comments
-
Well for the boiler you decided the site put in the piping and electric supply then the plaster then put in the boiler.0
-
and for the whole house? Does the plumbing get done first, then the CH, electrics & plastering always last?"Science is a wonderful thing if one does not have to earn one's living at it" Einstein 19510
-
Ask to see CIPHE (Chartered Institute of Plumbing & Heating Engineering)0
-
thankyou so much - very useful!"Science is a wonderful thing if one does not have to earn one's living at it" Einstein 19510
-
1.Pipe work first fix
2.Electrics first fix
3.Plaster
4.electric second fix
5.boiler installation.
6.Plumbing Second fix0
This discussion has been closed.
Confirm your email address to Create Threads and Reply
Categories
- All Categories
- 352.5K Banking & Borrowing
- 253.7K Reduce Debt & Boost Income
- 454.5K Spending & Discounts
- 245.5K Work, Benefits & Business
- 601.4K Mortgages, Homes & Bills
- 177.6K Life & Family
- 259.4K Travel & Transport
- 1.5M Hobbies & Leisure
- 16K Discuss & Feedback
- 37.7K Read-Only Boards