New Central Heating quote - is this reasonable?
Options
eshzaina
Posts: 21 Forumite
Hi all,
I have been searching these forums for a while now and just about to purchase our first home and could really do with some advice. The house needs gutting out and the old central heating sytem needs to come out and be replaced with a new combi system.
We have had a few guys come round and recieved the following quote from one. I would really appreciate your thoughts on this and if you think its a reasonable price for the work included.
Many Thanks in advance.
PREPARATION
Drain down existing central heating system, disconnect existing boiler and associated flue.
Disconnect existing hot water cylinder, cut out and remove any redundant pipes.
Disconnect cold water storage tank; convert all cold water supplies to direct mains.
Disconnect existing radiators and redundant pipe work.
TO SUPPLY AND INSTALL
Valliant 831 or 837 eco-tec plus condensing combination boiler, position to be decided.
GAS SUPPLY
Install 22mm gas supply to boiler to obtain 20 Mbar working pressure, gas rate boiler and carry out soundness test at meter.
Leave new cooker supply.
FLUE
Install horizontal fan flue assembly to outside.
DOMESTIC HOT AND COLD WATER
From incoming mains supply run new cold supply to all appliances in kitchen, boiler and all appliances in bathroom.
From new boiler position run new hot water supply to all appliances in kitchen and bathroom.
ElECTRICAL INSTALLATION
Wire boiler into existing fuse spur.
Earth cross bond pipe-work under boiler
HEATING
From new boiler position run new 22mm & 15mm flow and return to the following radiators.
Lounge- 600 x 1400 DC
Kit/diner - 600 x 1300 DC x3
Hall - 600 x 1200 DP+
Study - 600 x 1300 DC
WC - 400 x 700 chrome towel rail
Bedroom1 600 x 700 DP+
Bedroom2 600 x 1300 DC
Bedroom3 600 x 1100 DC
Bedroom4 600 x 1200 DC
Bathroom 600 x 1500 chrome towel rail
CONTROLS
Supply and install thermostatic radiator valves to all radiators except hall.
Supply and install lock shield valves to all radiators.
Supply and install wireless room stat in hall.
Supply and install valliant built in 130 time switch.
CHEMICAL AND INHIBITOR REQUIREMENT
Manually hot flush system and boiler as per manufacterers specification.
Add Fernox inhibitor to system.
COMMISIONING
The system will be tested, and commissioned to boiler manufacteres instructions on completion of works.
WARRANTY
The installation will be installed to current Gas Safe register regulations, manufacteres specification and will be covered by a 2 year guarantee on parts and labour.
BUILDING WORKS
Make good to wall where old flue was removed
WASTE MATERIALS
Remove all redundant material from site.
TOTAL COST: £4950.00 PLUS VAT
I have been searching these forums for a while now and just about to purchase our first home and could really do with some advice. The house needs gutting out and the old central heating sytem needs to come out and be replaced with a new combi system.
We have had a few guys come round and recieved the following quote from one. I would really appreciate your thoughts on this and if you think its a reasonable price for the work included.
Many Thanks in advance.
PREPARATION
Drain down existing central heating system, disconnect existing boiler and associated flue.
Disconnect existing hot water cylinder, cut out and remove any redundant pipes.
Disconnect cold water storage tank; convert all cold water supplies to direct mains.
Disconnect existing radiators and redundant pipe work.
TO SUPPLY AND INSTALL
Valliant 831 or 837 eco-tec plus condensing combination boiler, position to be decided.
GAS SUPPLY
Install 22mm gas supply to boiler to obtain 20 Mbar working pressure, gas rate boiler and carry out soundness test at meter.
Leave new cooker supply.
FLUE
Install horizontal fan flue assembly to outside.
DOMESTIC HOT AND COLD WATER
From incoming mains supply run new cold supply to all appliances in kitchen, boiler and all appliances in bathroom.
From new boiler position run new hot water supply to all appliances in kitchen and bathroom.
ElECTRICAL INSTALLATION
Wire boiler into existing fuse spur.
Earth cross bond pipe-work under boiler
HEATING
From new boiler position run new 22mm & 15mm flow and return to the following radiators.
Lounge- 600 x 1400 DC
Kit/diner - 600 x 1300 DC x3
Hall - 600 x 1200 DP+
Study - 600 x 1300 DC
WC - 400 x 700 chrome towel rail
Bedroom1 600 x 700 DP+
Bedroom2 600 x 1300 DC
Bedroom3 600 x 1100 DC
Bedroom4 600 x 1200 DC
Bathroom 600 x 1500 chrome towel rail
CONTROLS
Supply and install thermostatic radiator valves to all radiators except hall.
Supply and install lock shield valves to all radiators.
Supply and install wireless room stat in hall.
Supply and install valliant built in 130 time switch.
CHEMICAL AND INHIBITOR REQUIREMENT
Manually hot flush system and boiler as per manufacterers specification.
Add Fernox inhibitor to system.
COMMISIONING
The system will be tested, and commissioned to boiler manufacteres instructions on completion of works.
WARRANTY
The installation will be installed to current Gas Safe register regulations, manufacteres specification and will be covered by a 2 year guarantee on parts and labour.
BUILDING WORKS
Make good to wall where old flue was removed
WASTE MATERIALS
Remove all redundant material from site.
TOTAL COST: £4950.00 PLUS VAT
0
Comments
-
expensive for oop north.
probably cheap for west london.Get some gorm.0 -
Forgot to mention I am in North London
And also this includes the supply of all materials and labour.
Thanks
Esh0 -
Hi all,
I have been searching these forums for a while now and just about to purchase our first home and could really do with some advice. The house needs gutting out and the old central heating sytem needs to come out and be replaced with a new combi system.
We have had a few guys come round and recieved the following quote from one. I would really appreciate your thoughts on this and if you think its a reasonable price for the work included.
Many Thanks in advance.
PREPARATION
Drain down existing central heating system, disconnect existing boiler and associated flue.
Disconnect existing hot water cylinder, cut out and remove any redundant pipes.
Disconnect cold water storage tank; convert all cold water supplies to direct mains.
Disconnect existing radiators and redundant pipe work.
TO SUPPLY AND INSTALL
Valliant 831 or 837 eco-tec plus condensing combination boiler, position to be decided.
GAS SUPPLY
Install 22mm gas supply to boiler to obtain 20 Mbar working pressure, gas rate boiler and carry out soundness test at meter.
Leave new cooker supply.
FLUE
Install horizontal fan flue assembly to outside.
DOMESTIC HOT AND COLD WATER
From incoming mains supply run new cold supply to all appliances in kitchen, boiler and all appliances in bathroom.
From new boiler position run new hot water supply to all appliances in kitchen and bathroom.
ElECTRICAL INSTALLATION
Wire boiler into existing fuse spur.
Earth cross bond pipe-work under boiler
HEATING
From new boiler position run new 22mm & 15mm flow and return to the following radiators.
Lounge- 600 x 1400 DC
Kit/diner - 600 x 1300 DC x3
Hall - 600 x 1200 DP+
Study - 600 x 1300 DC
WC - 400 x 700 chrome towel rail
Bedroom1 600 x 700 DP+
Bedroom2 600 x 1300 DC
Bedroom3 600 x 1100 DC
Bedroom4 600 x 1200 DC
Bathroom 600 x 1500 chrome towel rail
CONTROLS
Supply and install thermostatic radiator valves to all radiators except hall.
Supply and install lock shield valves to all radiators.
Supply and install wireless room stat in hall.
Supply and install valliant built in 130 time switch.
CHEMICAL AND INHIBITOR REQUIREMENT
Manually hot flush system and boiler as per manufacterers specification.
Add Fernox inhibitor to system.
COMMISIONING
The system will be tested, and commissioned to boiler manufacteres instructions on completion of works.
WARRANTY
The installation will be installed to current Gas Safe register regulations, manufacteres specification and will be covered by a 2 year guarantee on parts and labour.
BUILDING WORKS
Make good to wall where old flue was removed
WASTE MATERIALS
Remove all redundant material from site.
TOTAL COST: £4950.00 PLUS VAT
Good evening: forget the Vaillant controls and go with a Honeywell CM 927 wireless programmable room stat. Vaillant recommends a scale inhibitor as you are in a hard water area. A magnetic filter i.e. Boiler Buddy or Spirovent is also a worthy addition....decent price for London. Compare each quote like for like.
HTH
CanuckleheadAsk to see CIPHE (Chartered Institute of Plumbing & Heating Engineering)0 -
I am suspicious of the 22mm gas pipe, especially for the 837.
The quote says that the installation site has yet to be decided, so how can the installer know what size the gas pipe should be yet?0 -
Thanks for the replies.
We were originally thinking about moving the boiler to the garage which is attached to the side of the kitchen, but will just keep it boxed in a cirner of the kitchen.
I take it the honeywells are better quality than the valliants?0 -
Hi all,
I have been searching these forums for a while now and just about to purchase our first home and could really do with some advice. The house needs gutting out and the old central heating sytem needs to come out and be replaced with a new combi system.
We have had a few guys come round and recieved the following quote from one. I would really appreciate your thoughts on this and if you think its a reasonable price for the work included.
Many Thanks in advance.
PREPARATION
Drain down existing central heating system, disconnect existing boiler and associated flue.
Disconnect existing hot water cylinder, cut out and remove any redundant pipes.
Disconnect cold water storage tank; convert all cold water supplies to direct mains.
Disconnect existing radiators and redundant pipe work.
TO SUPPLY AND INSTALL
Valliant 831 or 837 eco-tec plus condensing combination boiler, position to be decided.
GAS SUPPLY
Install 22mm gas supply to boiler to obtain 20 Mbar working pressure, gas rate boiler and carry out soundness test at meter.
Leave new cooker supply.
FLUE
Install horizontal fan flue assembly to outside.
DOMESTIC HOT AND COLD WATER
From incoming mains supply run new cold supply to all appliances in kitchen, boiler and all appliances in bathroom.
From new boiler position run new hot water supply to all appliances in kitchen and bathroom.
ElECTRICAL INSTALLATION
Wire boiler into existing fuse spur.
Earth cross bond pipe-work under boiler
HEATING
From new boiler position run new 22mm & 15mm flow and return to the following radiators.
Lounge- 600 x 1400 DC
Kit/diner - 600 x 1300 DC x3
Hall - 600 x 1200 DP+
Study - 600 x 1300 DC
WC - 400 x 700 chrome towel rail
Bedroom1 600 x 700 DP+
Bedroom2 600 x 1300 DC
Bedroom3 600 x 1100 DC
Bedroom4 600 x 1200 DC
Bathroom 600 x 1500 chrome towel rail
CONTROLS
Supply and install thermostatic radiator valves to all radiators except hall.
Supply and install lock shield valves to all radiators.
Supply and install wireless room stat in hall.
Supply and install valliant built in 130 time switch.
CHEMICAL AND INHIBITOR REQUIREMENT
Manually hot flush system and boiler as per manufacterers specification.
Add Fernox inhibitor to system.
COMMISIONING
The system will be tested, and commissioned to boiler manufacteres instructions on completion of works.
WARRANTY
The installation will be installed to current Gas Safe register regulations, manufacteres specification and will be covered by a 2 year guarantee on parts and labour.
BUILDING WORKS
Make good to wall where old flue was removed
WASTE MATERIALS
Remove all redundant material from site.
TOTAL COST: £4950.00 PLUS VAT
The price seems very high to me but i am up northX British Gas engineer and X BG sales adviser.
Please don,t let this put you off.0 -
I can add that the Honeywell CMT 927 (7 day programmer) is a very good investment on a new install. It's very easy to programme, it can have 6 different temperatures over each 24 hour period and each of the seven days can be different. Plus its wireless so can go in any room (ours is in the lounge).
A friend has the Vaillant programmer and has to get the instructions out each time to change things (he's an IT engineer!!)
I've recently had my old boiler removed from the loft (including all tanks etc) in prep for loft conversion.- New Vaillant 831 ecotec plus installed in a bedroom (its very quiet)
- Whole system powerflushed (took just under one day)
- Fernox TF1 return flow magnetic filter installed
- All Pipework boxed in.
- New thermostatic radiator valves on 8 radiators
- Got a 5 year warranty as installer is vaillant registered, + one year added for boiler scrappage,
0 -
We've just had very similar in the north west for ~£3000, towel rad and magnaclean supplied though.
Get some more quotes first0
This discussion has been closed.
Categories
- All Categories
- 343.2K Banking & Borrowing
- 250.1K Reduce Debt & Boost Income
- 449.7K Spending & Discounts
- 235.3K Work, Benefits & Business
- 608.1K Mortgages, Homes & Bills
- 173.1K Life & Family
- 247.9K Travel & Transport
- 1.5M Hobbies & Leisure
- 15.9K Discuss & Feedback
- 15.1K Coronavirus Support Boards