Standard DNO timing?

Jonboy1889
Jonboy1889 Posts: 168 Forumite
Part of the Furniture 100 Posts Name Dropper Combo Breaker
edited 4 May 2023 at 11:46AM in Green & ethical MoneySaving
Can anyone give an idea of how long the standard DNO form takes to come back for system 3.6kw?

Comments

  • Raxiel
    Raxiel Posts: 1,403 Forumite
    Eighth Anniversary 1,000 Posts Name Dropper Photogenic
    I assume the forum software got confused and that should be < 3.6kW?
    In my case, National Grid (formerly Western Power) responded to my installers G98 with a PDF letter in an email within a day. I don't know exactly when the installer submitted it but I received it 24 hours after commissioning, about an hour after I'd paid.

    This was last October
    3.6 kW PV in the Midlands - 9x Sharp 400W black panels - 6x facing SE and 3x facing SW, Solaredge Optimisers and Inverter. 400W Derril Water (one day). Octopus Flux
  • Can anyone give an idea of how long the standard DNO form takes to come back for system 3.6kw?
    A solar PV system with an inverter limit of 3.86kW or less per phase does not need DNO approval. The installer needs to notify the DNO once the array has been installed. A DNO acknowledgement is needed by the supplier to obtain an export MPAN.
  • Jonboy1889
    Jonboy1889 Posts: 168 Forumite
    Part of the Furniture 100 Posts Name Dropper Combo Breaker
    edited 25 October 2023 at 9:41PM
    Can anyone give an idea of how long the standard DNO form takes to come back for system 3.6kw?
    A solar PV system with an inverter limit of 3.86kW or less per phase does not need DNO approval. The installer needs to notify the DNO once the array has been installed. A DNO acknowledgement is needed by the supplier to obtain an export MPAN.
    Thanks- that was what I meant- how long for the DNO acknowledgement to arrive?
  • [Deleted User]
    [Deleted User] Posts: 0 Newbie
    1,000 Posts Third Anniversary Name Dropper
    edited 25 October 2023 at 9:41PM
    Can anyone give an idea of how long the standard DNO form takes to come back for system 3.6kw?
    A solar PV system with an inverter limit of 3.86kW or less per phase does not need DNO approval. The installer needs to notify the DNO once the array has been installed. A DNO acknowledgement is needed by the supplier to obtain an export MPAN.
    Thanks- that was what I meant- how long for the DNO acknowledgement to arrive?
    It varies by DNO. 
Meet your Ambassadors

🚀 Getting Started

Hi new member!

Our Getting Started Guide will help you get the most out of the Forum

Categories

  • All Categories
  • 349.9K Banking & Borrowing
  • 252.7K Reduce Debt & Boost Income
  • 453.1K Spending & Discounts
  • 242.9K Work, Benefits & Business
  • 619.7K Mortgages, Homes & Bills
  • 176.4K Life & Family
  • 255.8K Travel & Transport
  • 1.5M Hobbies & Leisure
  • 16.1K Discuss & Feedback
  • 15.1K Coronavirus Support Boards

Is this how you want to be seen?

We see you are using a default avatar. It takes only a few seconds to pick a picture.