📨 Have you signed up to the Forum's new Email Digest yet? Get a selection of trending threads sent straight to your inbox daily, weekly or monthly!

DNO request

Options
My solar panels have been fitted and already generating quite a bit.
I have my MCS -  i have been informed that the email regarding the DNO has been sent. Does anyone know generally how long these are taking to get a response. Obviously i need before I can sort an outgoing tariff.

Comments

  • It took my DNO (SPEN) 3 months to confirm that it was happy to sign off on the commissioning data (PV and battery). It then took my supplier a further month to get an export MPAN from the DNO. Other DNOs may be faster.
  • Alnat1
    Alnat1 Posts: 3,870 Forumite
    1,000 Posts Third Anniversary Photogenic Name Dropper
    About 3 weeks for Northern Power back in March
    Barnsley, South Yorkshire
    Solar PV 5.25kWp SW facing (14 x 375) Lux 3.6kw hybrid inverter installed Mar 22 and 9.6kw Pylontech battery 
    Daikin 8kW ASHP installed Jan 25
    Octopus Cosy/Fixed Outgoing 
Meet your Ambassadors

🚀 Getting Started

Hi new member!

Our Getting Started Guide will help you get the most out of the Forum

Categories

  • All Categories
  • 351.1K Banking & Borrowing
  • 253.2K Reduce Debt & Boost Income
  • 453.7K Spending & Discounts
  • 244.1K Work, Benefits & Business
  • 599.2K Mortgages, Homes & Bills
  • 177K Life & Family
  • 257.5K Travel & Transport
  • 1.5M Hobbies & Leisure
  • 16.1K Discuss & Feedback
  • 37.6K Read-Only Boards

Is this how you want to be seen?

We see you are using a default avatar. It takes only a few seconds to pick a picture.