DNO request

My solar panels have been fitted and already generating quite a bit.
I have my MCS -  i have been informed that the email regarding the DNO has been sent. Does anyone know generally how long these are taking to get a response. Obviously i need before I can sort an outgoing tariff.

Replies

  • DolorDolor Forumite
    5.8K Posts
    1,000 Posts Third Anniversary Name Dropper
    Forumite
    It took my DNO (SPEN) 3 months to confirm that it was happy to sign off on the commissioning data (PV and battery). It then took my supplier a further month to get an export MPAN from the DNO. Other DNOs may be faster.
  • Alnat1Alnat1 Forumite
    2.3K Posts
    1,000 Posts First Anniversary Name Dropper
    Forumite
    About 3 weeks for Northern Power back in March
    Barnsley, South Yorkshire
    Solar PV 5.25kWp SW facing (14 x 375 Longi) Lux 3.6kw hybrid inverter and 4.8kw Pylontech battery storage installed March 22
    Octopus Flux electric and Tracker gas
Sign In or Register to comment.
Latest MSE News and Guides

Did you know there's an MSE app?

It's free & available on iOS & Android

MSE App

Regifting: good idea or not?

Add your two cents to the discussion

MSE Forum

Energy Price Guarantee calculator

How much you'll likely pay from April

MSE Tools